SPA Electricity Demand and Generation Mix
SPA demand was 9 MW in the hour starting 5 Nov 2026, 07:00 CST (UTC-06:00). Hydro was the largest source in the hour starting 4 Nov 2026, 22:00 CST (UTC-06:00), at 100% of generation. Operator data is hourly and provisional, and may be revised.
Key Facts
- SPA is a balancing authority in the United States, part of the EIA Central region.
- In the hour starting 5 Nov 2026, 07:00 CST (UTC-06:00), demand in SPA was 9 MW, against a day-ahead forecast of 24 MW.
- Hydro supplied 100.0% of SPA's generation in the hour starting 4 Nov 2026, 22:00 CST (UTC-06:00).
- Demand in SPA totalled 197 GWh in 2024.
- Hydro supplied 56.6% of SPA's generation in 2024.
- The highest daily demand in SPA from 2019 onward was 2.80 GWh, on 2021-02-15 (15 February 2021).
- The highest hourly demand in SPA since 2026-06-16 (16 June 2026) was 59 MW, in the hour starting 17 Jun 2026, 11:00 CDT (UTC-05:00).
- Solar's highest share of SPA's daily generation from 2019 onward was 100.0%, on 2024-06-03 (3 June 2024).
- Wind's highest share of SPA's daily generation from 2019 onward was 100.0%, on 2024-06-03 (3 June 2024).
Latest Demand
Hourly operator dataLatest hour known when this page was built: 5 Nov 2026, 07:00 CST (UTC-06:00).
Source: U.S. Energy Information Administration (EIA). (US Government work, public domain) Data as of 2026-11-05T13:00:00Z.
Generation by Source
Latest hour with generation by source: 4 Nov 2026, 22:00 CST (UTC-06:00)| Source | Output | Share |
|---|---|---|
| Hydro | 8 MW | 100.0% |
| Total from these sources | 8 MW | |
| Net interchange | -10 MW | net imports |
EIA publishes generation by source 10 or more hours after demand, so this hour can be earlier than the latest demand hour. Net interchange is positive when SPA exports.
The sources reported in this hour add up to 44% of demand, so the generation report for SPA looks incomplete and the shares above are shares of what was reported.
Source: U.S. Energy Information Administration (EIA). (US Government work, public domain) Data as of 2026-11-05T04:00:00Z.
Last 30 Days, Hourly
Times in UTCShow the data table (720 rows)
| Hour starting (UTC) | Demand |
|---|---|
| 2026-10-06T15:00Z | 15 MW |
| 2026-10-06T16:00Z | 15 MW |
| 2026-10-06T17:00Z | 12 MW |
| 2026-10-06T18:00Z | 12 MW |
| 2026-10-06T19:00Z | 10 MW |
| 2026-10-06T20:00Z | 9 MW |
| 2026-10-06T21:00Z | 23 MW |
| 2026-10-06T22:00Z | 13 MW |
| 2026-10-06T23:00Z | 17 MW |
| 2026-10-07T00:00Z | 7 MW |
| 2026-10-07T01:00Z | 20 MW |
| 2026-10-07T02:00Z | 24 MW |
| 2026-10-07T03:00Z | 18 MW |
| 2026-10-07T04:00Z | 18 MW |
| 2026-10-07T05:00Z | 23 MW |
| 2026-10-07T06:00Z | 19 MW |
| 2026-10-07T07:00Z | 25 MW |
| 2026-10-07T08:00Z | 16 MW |
| 2026-10-07T09:00Z | 23 MW |
| 2026-10-07T10:00Z | 22 MW |
| 2026-10-07T11:00Z | 17 MW |
| 2026-10-07T12:00Z | 19 MW |
| 2026-10-07T13:00Z | 6 MW |
| 2026-10-07T14:00Z | 20 MW |
| 2026-10-07T15:00Z | 15 MW |
| 2026-10-07T16:00Z | 18 MW |
| 2026-10-07T17:00Z | 13 MW |
| 2026-10-07T18:00Z | 24 MW |
| 2026-10-07T19:00Z | 13 MW |
| 2026-10-07T20:00Z | 11 MW |
| 2026-10-07T21:00Z | 16 MW |
| 2026-10-07T22:00Z | 23 MW |
| 2026-10-07T23:00Z | 25 MW |
| 2026-10-08T00:00Z | 18 MW |
| 2026-10-08T01:00Z | 15 MW |
| 2026-10-08T02:00Z | 9 MW |
| 2026-10-08T03:00Z | 14 MW |
| 2026-10-08T04:00Z | 16 MW |
| 2026-10-08T05:00Z | 16 MW |
| 2026-10-08T06:00Z | 14 MW |
| 2026-10-08T07:00Z | 11 MW |
| 2026-10-08T08:00Z | 14 MW |
| 2026-10-08T09:00Z | 18 MW |
| 2026-10-08T10:00Z | 8 MW |
| 2026-10-08T11:00Z | 12 MW |
| 2026-10-08T12:00Z | 14 MW |
| 2026-10-08T13:00Z | 18 MW |
| 2026-10-08T14:00Z | 18 MW |
| 2026-10-08T15:00Z | 30 MW |
| 2026-10-08T16:00Z | 19 MW |
| 2026-10-08T17:00Z | 25 MW |
| 2026-10-08T18:00Z | 16 MW |
| 2026-10-08T19:00Z | 20 MW |
| 2026-10-08T20:00Z | 24 MW |
| 2026-10-08T21:00Z | 20 MW |
| 2026-10-08T22:00Z | 24 MW |
| 2026-10-08T23:00Z | 19 MW |
| 2026-10-09T00:00Z | 12 MW |
| 2026-10-09T01:00Z | 16 MW |
| 2026-10-09T02:00Z | 13 MW |
| 2026-10-09T03:00Z | 22 MW |
| 2026-10-09T04:00Z | 8 MW |
| 2026-10-09T05:00Z | 21 MW |
| 2026-10-09T06:00Z | 15 MW |
| 2026-10-09T07:00Z | 16 MW |
| 2026-10-09T08:00Z | 22 MW |
| 2026-10-09T09:00Z | 17 MW |
| 2026-10-09T10:00Z | 20 MW |
| 2026-10-09T11:00Z | 18 MW |
| 2026-10-09T12:00Z | 18 MW |
| 2026-10-09T13:00Z | 12 MW |
| 2026-10-09T14:00Z | 20 MW |
| 2026-10-09T15:00Z | 12 MW |
| 2026-10-09T16:00Z | 17 MW |
| 2026-10-09T17:00Z | 12 MW |
| 2026-10-09T18:00Z | 11 MW |
| 2026-10-09T19:00Z | 10 MW |
| 2026-10-09T20:00Z | 14 MW |
| 2026-10-09T21:00Z | 7 MW |
| 2026-10-09T22:00Z | 24 MW |
| 2026-10-09T23:00Z | 18 MW |
| 2026-10-10T00:00Z | 13 MW |
| 2026-10-10T01:00Z | 15 MW |
| 2026-10-10T02:00Z | 23 MW |
| 2026-10-10T03:00Z | 17 MW |
| 2026-10-10T04:00Z | 20 MW |
| 2026-10-10T05:00Z | 24 MW |
| 2026-10-10T06:00Z | 27 MW |
| 2026-10-10T07:00Z | 25 MW |
| 2026-10-10T08:00Z | 20 MW |
| 2026-10-10T09:00Z | 30 MW |
| 2026-10-10T10:00Z | 20 MW |
| 2026-10-10T11:00Z | 20 MW |
| 2026-10-10T12:00Z | 24 MW |
| 2026-10-10T13:00Z | 26 MW |
| 2026-10-10T14:00Z | 18 MW |
| 2026-10-10T15:00Z | 22 MW |
| 2026-10-10T16:00Z | 29 MW |
| 2026-10-10T17:00Z | 17 MW |
| 2026-10-10T18:00Z | 19 MW |
| 2026-10-10T19:00Z | 16 MW |
| 2026-10-10T20:00Z | 18 MW |
| 2026-10-10T21:00Z | 20 MW |
| 2026-10-10T22:00Z | 21 MW |
| 2026-10-10T23:00Z | 18 MW |
| 2026-10-11T00:00Z | 21 MW |
| 2026-10-11T01:00Z | 13 MW |
| 2026-10-11T02:00Z | 23 MW |
| 2026-10-11T03:00Z | 13 MW |
| 2026-10-11T04:00Z | 29 MW |
| 2026-10-11T05:00Z | 20 MW |
| 2026-10-11T06:00Z | 22 MW |
| 2026-10-11T07:00Z | 23 MW |
| 2026-10-11T08:00Z | 21 MW |
| 2026-10-11T09:00Z | 22 MW |
| 2026-10-11T10:00Z | 21 MW |
| 2026-10-11T11:00Z | 22 MW |
| 2026-10-11T12:00Z | 19 MW |
| 2026-10-11T13:00Z | 26 MW |
| 2026-10-11T14:00Z | 14 MW |
| 2026-10-11T15:00Z | 18 MW |
| 2026-10-11T16:00Z | 20 MW |
| 2026-10-11T17:00Z | 12 MW |
| 2026-10-11T18:00Z | 21 MW |
| 2026-10-11T19:00Z | 19 MW |
| 2026-10-11T20:00Z | 11 MW |
| 2026-10-11T21:00Z | 17 MW |
| 2026-10-11T22:00Z | 22 MW |
| 2026-10-11T23:00Z | 19 MW |
| 2026-10-12T00:00Z | 16 MW |
| 2026-10-12T01:00Z | 25 MW |
| 2026-10-12T02:00Z | 12 MW |
| 2026-10-12T03:00Z | 22 MW |
| 2026-10-12T04:00Z | 20 MW |
| 2026-10-12T05:00Z | 27 MW |
| 2026-10-12T06:00Z | 18 MW |
| 2026-10-12T07:00Z | 30 MW |
| 2026-10-12T08:00Z | 18 MW |
| 2026-10-12T09:00Z | 27 MW |
| 2026-10-12T10:00Z | 25 MW |
| 2026-10-12T11:00Z | 28 MW |
| 2026-10-12T12:00Z | 18 MW |
| 2026-10-12T13:00Z | 27 MW |
| 2026-10-12T14:00Z | 16 MW |
| 2026-10-12T15:00Z | 23 MW |
| 2026-10-12T16:00Z | 15 MW |
| 2026-10-12T17:00Z | 30 MW |
| 2026-10-12T18:00Z | 12 MW |
| 2026-10-12T19:00Z | 10 MW |
| 2026-10-12T20:00Z | 14 MW |
| 2026-10-12T21:00Z | 27 MW |
| 2026-10-12T22:00Z | 37 MW |
| 2026-10-12T23:00Z | 19 MW |
| 2026-10-13T00:00Z | 21 MW |
| 2026-10-13T01:00Z | 16 MW |
| 2026-10-13T02:00Z | 20 MW |
| 2026-10-13T03:00Z | 19 MW |
| 2026-10-13T04:00Z | 28 MW |
| 2026-10-13T05:00Z | 17 MW |
| 2026-10-13T06:00Z | 18 MW |
| 2026-10-13T07:00Z | 22 MW |
| 2026-10-13T08:00Z | 26 MW |
| 2026-10-13T09:00Z | 13 MW |
| 2026-10-13T10:00Z | 28 MW |
| 2026-10-13T11:00Z | 11 MW |
| 2026-10-13T12:00Z | 29 MW |
| 2026-10-13T13:00Z | 14 MW |
| 2026-10-13T14:00Z | 22 MW |
| 2026-10-13T15:00Z | 23 MW |
| 2026-10-13T16:00Z | 21 MW |
| 2026-10-13T17:00Z | 17 MW |
| 2026-10-13T18:00Z | 24 MW |
| 2026-10-13T19:00Z | 28 MW |
| 2026-10-13T20:00Z | 27 MW |
| 2026-10-13T21:00Z | 28 MW |
| 2026-10-13T22:00Z | 41 MW |
| 2026-10-13T23:00Z | 39 MW |
| 2026-10-14T00:00Z | 21 MW |
| 2026-10-14T01:00Z | 15 MW |
| 2026-10-14T02:00Z | 20 MW |
| 2026-10-14T03:00Z | 19 MW |
| 2026-10-14T04:00Z | 14 MW |
| 2026-10-14T05:00Z | 23 MW |
| 2026-10-14T06:00Z | 24 MW |
| 2026-10-14T07:00Z | 19 MW |
| 2026-10-14T08:00Z | 24 MW |
| 2026-10-14T09:00Z | 16 MW |
| 2026-10-14T10:00Z | 18 MW |
| 2026-10-14T11:00Z | 21 MW |
| 2026-10-14T12:00Z | 28 MW |
| 2026-10-14T13:00Z | 16 MW |
| 2026-10-14T14:00Z | 22 MW |
| 2026-10-14T15:00Z | 26 MW |
| 2026-10-14T16:00Z | 22 MW |
| 2026-10-14T17:00Z | 12 MW |
| 2026-10-14T18:00Z | 26 MW |
| 2026-10-14T19:00Z | 30 MW |
| 2026-10-14T20:00Z | 41 MW |
| 2026-10-14T21:00Z | 32 MW |
| 2026-10-14T22:00Z | 39 MW |
| 2026-10-14T23:00Z | 38 MW |
| 2026-10-15T00:00Z | 22 MW |
| 2026-10-15T01:00Z | 23 MW |
| 2026-10-15T02:00Z | 22 MW |
| 2026-10-15T03:00Z | 16 MW |
| 2026-10-15T04:00Z | 26 MW |
| 2026-10-15T05:00Z | 20 MW |
| 2026-10-15T06:00Z | 21 MW |
| 2026-10-15T07:00Z | 16 MW |
| 2026-10-15T08:00Z | 23 MW |
| 2026-10-15T09:00Z | 19 MW |
| 2026-10-15T10:00Z | 14 MW |
| 2026-10-15T11:00Z | 26 MW |
| 2026-10-15T12:00Z | 26 MW |
| 2026-10-15T13:00Z | 17 MW |
| 2026-10-15T14:00Z | 27 MW |
| 2026-10-15T15:00Z | 25 MW |
| 2026-10-15T16:00Z | 16 MW |
| 2026-10-15T17:00Z | 31 MW |
| 2026-10-15T18:00Z | 23 MW |
| 2026-10-15T19:00Z | 18 MW |
| 2026-10-15T20:00Z | 27 MW |
| 2026-10-15T21:00Z | 39 MW |
| 2026-10-15T22:00Z | 38 MW |
| 2026-10-15T23:00Z | 42 MW |
| 2026-10-16T00:00Z | 24 MW |
| 2026-10-16T01:00Z | 33 MW |
| 2026-10-16T02:00Z | 27 MW |
| 2026-10-16T03:00Z | 23 MW |
| 2026-10-16T04:00Z | 21 MW |
| 2026-10-16T05:00Z | 27 MW |
| 2026-10-16T06:00Z | 25 MW |
| 2026-10-16T07:00Z | 30 MW |
| 2026-10-16T08:00Z | 26 MW |
| 2026-10-16T09:00Z | 28 MW |
| 2026-10-16T10:00Z | 30 MW |
| 2026-10-16T11:00Z | 28 MW |
| 2026-10-16T12:00Z | 26 MW |
| 2026-10-16T13:00Z | 27 MW |
| 2026-10-16T14:00Z | 24 MW |
| 2026-10-16T15:00Z | 26 MW |
| 2026-10-16T16:00Z | 22 MW |
| 2026-10-16T17:00Z | 38 MW |
| 2026-10-16T18:00Z | 25 MW |
| 2026-10-16T19:00Z | 24 MW |
| 2026-10-16T20:00Z | 24 MW |
| 2026-10-16T21:00Z | 32 MW |
| 2026-10-16T22:00Z | 34 MW |
| 2026-10-16T23:00Z | 34 MW |
| 2026-10-17T00:00Z | 26 MW |
| 2026-10-17T01:00Z | 17 MW |
| 2026-10-17T02:00Z | 19 MW |
| 2026-10-17T03:00Z | 23 MW |
| 2026-10-17T04:00Z | 18 MW |
| 2026-10-17T05:00Z | 15 MW |
| 2026-10-17T06:00Z | 11 MW |
| 2026-10-17T07:00Z | 16 MW |
| 2026-10-17T08:00Z | 20 MW |
| 2026-10-17T09:00Z | 10 MW |
| 2026-10-17T10:00Z | 24 MW |
| 2026-10-17T11:00Z | 26 MW |
| 2026-10-17T12:00Z | 22 MW |
| 2026-10-17T13:00Z | 20 MW |
| 2026-10-17T14:00Z | 26 MW |
| 2026-10-17T15:00Z | 13 MW |
| 2026-10-17T16:00Z | 11 MW |
| 2026-10-17T17:00Z | 18 MW |
| 2026-10-17T18:00Z | 9 MW |
| 2026-10-17T19:00Z | 13 MW |
| 2026-10-17T20:00Z | 13 MW |
| 2026-10-17T21:00Z | 1 MW |
| 2026-10-17T22:00Z | 27 MW |
| 2026-10-17T23:00Z | 21 MW |
| 2026-10-18T00:00Z | 8 MW |
| 2026-10-18T01:00Z | 12 MW |
| 2026-10-18T02:00Z | 13 MW |
| 2026-10-18T03:00Z | 19 MW |
| 2026-10-18T04:00Z | 9 MW |
| 2026-10-18T05:00Z | 12 MW |
| 2026-10-18T06:00Z | 32 MW |
| 2026-10-18T07:00Z | 19 MW |
| 2026-10-18T08:00Z | 18 MW |
| 2026-10-18T09:00Z | 14 MW |
| 2026-10-18T10:00Z | 24 MW |
| 2026-10-18T11:00Z | 20 MW |
| 2026-10-18T12:00Z | 19 MW |
| 2026-10-18T13:00Z | 12 MW |
| 2026-10-18T14:00Z | 26 MW |
| 2026-10-18T15:00Z | 18 MW |
| 2026-10-18T16:00Z | 18 MW |
| 2026-10-18T17:00Z | 19 MW |
| 2026-10-18T18:00Z | 17 MW |
| 2026-10-18T19:00Z | 17 MW |
| 2026-10-18T20:00Z | 24 MW |
| 2026-10-18T21:00Z | 23 MW |
| 2026-10-18T22:00Z | 29 MW |
| 2026-10-18T23:00Z | 24 MW |
| 2026-10-19T00:00Z | 25 MW |
| 2026-10-19T01:00Z | 22 MW |
| 2026-10-19T02:00Z | 21 MW |
| 2026-10-19T03:00Z | 22 MW |
| 2026-10-19T04:00Z | 23 MW |
| 2026-10-19T05:00Z | 33 MW |
| 2026-10-19T06:00Z | 30 MW |
| 2026-10-19T07:00Z | 19 MW |
| 2026-10-19T08:00Z | 36 MW |
| 2026-10-19T09:00Z | 26 MW |
| 2026-10-19T10:00Z | 31 MW |
| 2026-10-19T11:00Z | 23 MW |
| 2026-10-19T12:00Z | 24 MW |
| 2026-10-19T13:00Z | 28 MW |
| 2026-10-19T14:00Z | 12 MW |
| 2026-10-19T15:00Z | 20 MW |
| 2026-10-19T16:00Z | 7 MW |
| 2026-10-19T17:00Z | 12 MW |
| 2026-10-19T18:00Z | 20 MW |
| 2026-10-19T19:00Z | 2 MW |
| 2026-10-19T20:00Z | 19 MW |
| 2026-10-19T21:00Z | 15 MW |
| 2026-10-19T22:00Z | 10 MW |
| 2026-10-19T23:00Z | 28 MW |
| 2026-10-20T00:00Z | 17 MW |
| 2026-10-20T01:00Z | 9 MW |
| 2026-10-20T02:00Z | 3 MW |
| 2026-10-20T03:00Z | 17 MW |
| 2026-10-20T04:00Z | 18 MW |
| 2026-10-20T05:00Z | 6 MW |
| 2026-10-20T06:00Z | 19 MW |
| 2026-10-20T07:00Z | 18 MW |
| 2026-10-20T08:00Z | 10 MW |
| 2026-10-20T09:00Z | 14 MW |
| 2026-10-20T10:00Z | 17 MW |
| 2026-10-20T11:00Z | 12 MW |
| 2026-10-20T12:00Z | 15 MW |
| 2026-10-20T13:00Z | 14 MW |
| 2026-10-20T14:00Z | 16 MW |
| 2026-10-20T15:00Z | 8 MW |
| 2026-10-20T16:00Z | 20 MW |
| 2026-10-20T17:00Z | 11 MW |
| 2026-10-20T18:00Z | 16 MW |
| 2026-10-20T19:00Z | 17 MW |
| 2026-10-20T20:00Z | 9 MW |
| 2026-10-20T21:00Z | 18 MW |
| 2026-10-20T22:00Z | 18 MW |
| 2026-10-20T23:00Z | 16 MW |
| 2026-10-21T00:00Z | 22 MW |
| 2026-10-21T01:00Z | 6 MW |
| 2026-10-21T02:00Z | 18 MW |
| 2026-10-21T03:00Z | 8 MW |
| 2026-10-21T04:00Z | 13 MW |
| 2026-10-21T05:00Z | 17 MW |
| 2026-10-21T06:00Z | 20 MW |
| 2026-10-21T07:00Z | 11 MW |
| 2026-10-21T08:00Z | 15 MW |
| 2026-10-21T09:00Z | 12 MW |
| 2026-10-21T10:00Z | 18 MW |
| 2026-10-21T11:00Z | 12 MW |
| 2026-10-21T12:00Z | 21 MW |
| 2026-10-21T13:00Z | 9 MW |
| 2026-10-21T14:00Z | 16 MW |
| 2026-10-21T15:00Z | 10 MW |
| 2026-10-21T16:00Z | 9 MW |
| 2026-10-21T17:00Z | 17 MW |
| 2026-10-21T18:00Z | 4 MW |
| 2026-10-21T19:00Z | 10 MW |
| 2026-10-21T20:00Z | 11 MW |
| 2026-10-21T21:00Z | 19 MW |
| 2026-10-21T22:00Z | 13 MW |
| 2026-10-21T23:00Z | 17 MW |
| 2026-10-22T00:00Z | 18 MW |
| 2026-10-22T01:00Z | 5 MW |
| 2026-10-22T02:00Z | 9 MW |
| 2026-10-22T03:00Z | 12 MW |
| 2026-10-22T04:00Z | 13 MW |
| 2026-10-22T05:00Z | 6 MW |
| 2026-10-22T06:00Z | 10 MW |
| 2026-10-22T07:00Z | 15 MW |
| 2026-10-22T08:00Z | 10 MW |
| 2026-10-22T09:00Z | 7 MW |
| 2026-10-22T10:00Z | 14 MW |
| 2026-10-22T11:00Z | 10 MW |
| 2026-10-22T12:00Z | 9 MW |
| 2026-10-22T13:00Z | 13 MW |
| 2026-10-22T14:00Z | 10 MW |
| 2026-10-22T15:00Z | 8 MW |
| 2026-10-22T16:00Z | 14 MW |
| 2026-10-22T17:00Z | 11 MW |
| 2026-10-22T18:00Z | 12 MW |
| 2026-10-22T19:00Z | 13 MW |
| 2026-10-22T20:00Z | 11 MW |
| 2026-10-22T21:00Z | 8 MW |
| 2026-10-22T22:00Z | 10 MW |
| 2026-10-22T23:00Z | 15 MW |
| 2026-10-23T00:00Z | 11 MW |
| 2026-10-23T01:00Z | 12 MW |
| 2026-10-23T02:00Z | 14 MW |
| 2026-10-23T03:00Z | 3 MW |
| 2026-10-23T04:00Z | 17 MW |
| 2026-10-23T05:00Z | 9 MW |
| 2026-10-23T06:00Z | 13 MW |
| 2026-10-23T07:00Z | 21 MW |
| 2026-10-23T08:00Z | 6 MW |
| 2026-10-23T09:00Z | 19 MW |
| 2026-10-23T10:00Z | 15 MW |
| 2026-10-23T11:00Z | 19 MW |
| 2026-10-23T12:00Z | 13 MW |
| 2026-10-23T13:00Z | 5 MW |
| 2026-10-23T14:00Z | 17 MW |
| 2026-10-23T15:00Z | 4 MW |
| 2026-10-23T16:00Z | 6 MW |
| 2026-10-23T17:00Z | 6 MW |
| 2026-10-23T18:00Z | 12 MW |
| 2026-10-23T19:00Z | 7 MW |
| 2026-10-23T20:00Z | 18 MW |
| 2026-10-23T21:00Z | 12 MW |
| 2026-10-23T22:00Z | 18 MW |
| 2026-10-23T23:00Z | 15 MW |
| 2026-10-24T00:00Z | 14 MW |
| 2026-10-24T01:00Z | 15 MW |
| 2026-10-24T02:00Z | 9 MW |
| 2026-10-24T03:00Z | 19 MW |
| 2026-10-24T04:00Z | 19 MW |
| 2026-10-24T05:00Z | 14 MW |
| 2026-10-24T06:00Z | 21 MW |
| 2026-10-24T07:00Z | 14 MW |
| 2026-10-24T08:00Z | 22 MW |
| 2026-10-24T09:00Z | 27 MW |
| 2026-10-24T10:00Z | 15 MW |
| 2026-10-24T11:00Z | 18 MW |
| 2026-10-24T12:00Z | 7 MW |
| 2026-10-24T13:00Z | 21 MW |
| 2026-10-24T14:00Z | 7 MW |
| 2026-10-24T15:00Z | 17 MW |
| 2026-10-24T16:00Z | 0 MW |
| 2026-10-24T17:00Z | 13 MW |
| 2026-10-24T18:00Z | 4 MW |
| 2026-10-24T19:00Z | 11 MW |
| 2026-10-24T20:00Z | 8 MW |
| 2026-10-24T21:00Z | 0 MW |
| 2026-10-24T22:00Z | 17 MW |
| 2026-10-24T23:00Z | 7 MW |
| 2026-10-25T00:00Z | 9 MW |
| 2026-10-25T01:00Z | 18 MW |
| 2026-10-25T02:00Z | 19 MW |
| 2026-10-25T03:00Z | 10 MW |
| 2026-10-25T04:00Z | 17 MW |
| 2026-10-25T05:00Z | 16 MW |
| 2026-10-25T06:00Z | 16 MW |
| 2026-10-25T07:00Z | 12 MW |
| 2026-10-25T08:00Z | 10 MW |
| 2026-10-25T09:00Z | 15 MW |
| 2026-10-25T10:00Z | 24 MW |
| 2026-10-25T11:00Z | 9 MW |
| 2026-10-25T12:00Z | 10 MW |
| 2026-10-25T13:00Z | 15 MW |
| 2026-10-25T14:00Z | 13 MW |
| 2026-10-25T15:00Z | 12 MW |
| 2026-10-25T16:00Z | 9 MW |
| 2026-10-25T17:00Z | 15 MW |
| 2026-10-25T18:00Z | 14 MW |
| 2026-10-25T19:00Z | 12 MW |
| 2026-10-25T20:00Z | 9 MW |
| 2026-10-25T21:00Z | 9 MW |
| 2026-10-25T22:00Z | 11 MW |
| 2026-10-25T23:00Z | 18 MW |
| 2026-10-26T00:00Z | 10 MW |
| 2026-10-26T01:00Z | 16 MW |
| 2026-10-26T02:00Z | 12 MW |
| 2026-10-26T03:00Z | 14 MW |
| 2026-10-26T04:00Z | 15 MW |
| 2026-10-26T05:00Z | 18 MW |
| 2026-10-26T06:00Z | 16 MW |
| 2026-10-26T07:00Z | 18 MW |
| 2026-10-26T08:00Z | 17 MW |
| 2026-10-26T09:00Z | 14 MW |
| 2026-10-26T10:00Z | 15 MW |
| 2026-10-26T11:00Z | 19 MW |
| 2026-10-26T12:00Z | 13 MW |
| 2026-10-26T13:00Z | 15 MW |
| 2026-10-26T14:00Z | 7 MW |
| 2026-10-26T15:00Z | 18 MW |
| 2026-10-26T16:00Z | 6 MW |
| 2026-10-26T17:00Z | 11 MW |
| 2026-10-26T18:00Z | 14 MW |
| 2026-10-26T19:00Z | 16 MW |
| 2026-10-26T20:00Z | 7 MW |
| 2026-10-26T21:00Z | 15 MW |
| 2026-10-26T22:00Z | 20 MW |
| 2026-10-26T23:00Z | 11 MW |
| 2026-10-27T00:00Z | 14 MW |
| 2026-10-27T01:00Z | 17 MW |
| 2026-10-27T02:00Z | 13 MW |
| 2026-10-27T03:00Z | 18 MW |
| 2026-10-27T04:00Z | 18 MW |
| 2026-10-27T05:00Z | 23 MW |
| 2026-10-27T06:00Z | 12 MW |
| 2026-10-27T07:00Z | 0 MW |
| 2026-10-27T08:00Z | 12 MW |
| 2026-10-27T09:00Z | 18 MW |
| 2026-10-27T10:00Z | 19 MW |
| 2026-10-27T11:00Z | 11 MW |
| 2026-10-27T12:00Z | 18 MW |
| 2026-10-27T13:00Z | 10 MW |
| 2026-10-27T14:00Z | 14 MW |
| 2026-10-27T15:00Z | 15 MW |
| 2026-10-27T16:00Z | 22 MW |
| 2026-10-27T17:00Z | 7 MW |
| 2026-10-27T18:00Z | 21 MW |
| 2026-10-27T19:00Z | 8 MW |
| 2026-10-27T20:00Z | 19 MW |
| 2026-10-27T21:00Z | 16 MW |
| 2026-10-27T22:00Z | 8 MW |
| 2026-10-27T23:00Z | 21 MW |
| 2026-10-28T00:00Z | 19 MW |
| 2026-10-28T01:00Z | 22 MW |
| 2026-10-28T02:00Z | 8 MW |
| 2026-10-28T03:00Z | 22 MW |
| 2026-10-28T04:00Z | 23 MW |
| 2026-10-28T05:00Z | 23 MW |
| 2026-10-28T06:00Z | 22 MW |
| 2026-10-28T07:00Z | 24 MW |
| 2026-10-28T08:00Z | 24 MW |
| 2026-10-28T09:00Z | 18 MW |
| 2026-10-28T10:00Z | 28 MW |
| 2026-10-28T11:00Z | 18 MW |
| 2026-10-28T12:00Z | 21 MW |
| 2026-10-28T13:00Z | 17 MW |
| 2026-10-28T14:00Z | 15 MW |
| 2026-10-28T15:00Z | 9 MW |
| 2026-10-28T16:00Z | 20 MW |
| 2026-10-28T17:00Z | 20 MW |
| 2026-10-28T18:00Z | 12 MW |
| 2026-10-28T19:00Z | 21 MW |
| 2026-10-28T20:00Z | 19 MW |
| 2026-10-28T21:00Z | 13 MW |
| 2026-10-28T22:00Z | 22 MW |
| 2026-10-28T23:00Z | 13 MW |
| 2026-10-29T00:00Z | 22 MW |
| 2026-10-29T01:00Z | 17 MW |
| 2026-10-29T02:00Z | 19 MW |
| 2026-10-29T03:00Z | 18 MW |
| 2026-10-29T04:00Z | 18 MW |
| 2026-10-29T05:00Z | 25 MW |
| 2026-10-29T06:00Z | 25 MW |
| 2026-10-29T07:00Z | 16 MW |
| 2026-10-29T08:00Z | 24 MW |
| 2026-10-29T09:00Z | 20 MW |
| 2026-10-29T10:00Z | 21 MW |
| 2026-10-29T11:00Z | 22 MW |
| 2026-10-29T12:00Z | 19 MW |
| 2026-10-29T13:00Z | 7 MW |
| 2026-10-29T14:00Z | 22 MW |
| 2026-10-29T15:00Z | 16 MW |
| 2026-10-29T16:00Z | 5 MW |
| 2026-10-29T17:00Z | 11 MW |
| 2026-10-29T18:00Z | 16 MW |
| 2026-10-29T19:00Z | 9 MW |
| 2026-10-29T20:00Z | 10 MW |
| 2026-10-29T21:00Z | 24 MW |
| 2026-10-29T22:00Z | 12 MW |
| 2026-10-29T23:00Z | 13 MW |
| 2026-10-30T00:00Z | 8 MW |
| 2026-10-30T01:00Z | 23 MW |
| 2026-10-30T02:00Z | 14 MW |
| 2026-10-30T03:00Z | 14 MW |
| 2026-10-30T04:00Z | 17 MW |
| 2026-10-30T05:00Z | 22 MW |
| 2026-10-30T06:00Z | 15 MW |
| 2026-10-30T07:00Z | 24 MW |
| 2026-10-30T08:00Z | 19 MW |
| 2026-10-30T09:00Z | 19 MW |
| 2026-10-30T10:00Z | 21 MW |
| 2026-10-30T11:00Z | 31 MW |
| 2026-10-30T12:00Z | 15 MW |
| 2026-10-30T13:00Z | 21 MW |
| 2026-10-30T14:00Z | 19 MW |
| 2026-10-30T15:00Z | 13 MW |
| 2026-10-30T16:00Z | 7 MW |
| 2026-10-30T17:00Z | 13 MW |
| 2026-10-30T18:00Z | 17 MW |
| 2026-10-30T19:00Z | 7 MW |
| 2026-10-30T20:00Z | 10 MW |
| 2026-10-30T21:00Z | 17 MW |
| 2026-10-30T22:00Z | 11 MW |
| 2026-10-30T23:00Z | 18 MW |
| 2026-10-31T00:00Z | 13 MW |
| 2026-10-31T01:00Z | 10 MW |
| 2026-10-31T02:00Z | 6 MW |
| 2026-10-31T03:00Z | 13 MW |
| 2026-10-31T04:00Z | 16 MW |
| 2026-10-31T05:00Z | 11 MW |
| 2026-10-31T06:00Z | 24 MW |
| 2026-10-31T07:00Z | 12 MW |
| 2026-10-31T08:00Z | 13 MW |
| 2026-10-31T09:00Z | 18 MW |
| 2026-10-31T10:00Z | 16 MW |
| 2026-10-31T11:00Z | 13 MW |
| 2026-10-31T12:00Z | 24 MW |
| 2026-10-31T13:00Z | 13 MW |
| 2026-10-31T14:00Z | 10 MW |
| 2026-10-31T15:00Z | 18 MW |
| 2026-10-31T16:00Z | 15 MW |
| 2026-10-31T17:00Z | 18 MW |
| 2026-10-31T18:00Z | 7 MW |
| 2026-10-31T19:00Z | 14 MW |
| 2026-10-31T20:00Z | 10 MW |
| 2026-10-31T21:00Z | 20 MW |
| 2026-10-31T22:00Z | 12 MW |
| 2026-10-31T23:00Z | 9 MW |
| 2026-11-01T00:00Z | 15 MW |
| 2026-11-01T01:00Z | 12 MW |
| 2026-11-01T02:00Z | 16 MW |
| 2026-11-01T03:00Z | 13 MW |
| 2026-11-01T04:00Z | 20 MW |
| 2026-11-01T05:00Z | 8 MW |
| 2026-11-01T06:00Z | 11 MW |
| 2026-11-01T07:00Z | 14 MW |
| 2026-11-01T08:00Z | 8 MW |
| 2026-11-01T09:00Z | 12 MW |
| 2026-11-01T10:00Z | 12 MW |
| 2026-11-01T11:00Z | 15 MW |
| 2026-11-01T12:00Z | 28 MW |
| 2026-11-01T13:00Z | 6 MW |
| 2026-11-01T14:00Z | 17 MW |
| 2026-11-01T15:00Z | 12 MW |
| 2026-11-01T16:00Z | 9 MW |
| 2026-11-01T17:00Z | 10 MW |
| 2026-11-01T18:00Z | 14 MW |
| 2026-11-01T19:00Z | 21 MW |
| 2026-11-01T20:00Z | 9 MW |
| 2026-11-01T21:00Z | 30 MW |
| 2026-11-01T22:00Z | 13 MW |
| 2026-11-01T23:00Z | 15 MW |
| 2026-11-02T00:00Z | 12 MW |
| 2026-11-02T01:00Z | 6 MW |
| 2026-11-02T02:00Z | 10 MW |
| 2026-11-02T03:00Z | 19 MW |
| 2026-11-02T04:00Z | 11 MW |
| 2026-11-02T05:00Z | 13 MW |
| 2026-11-02T06:00Z | 19 MW |
| 2026-11-02T07:00Z | 20 MW |
| 2026-11-02T08:00Z | 21 MW |
| 2026-11-02T09:00Z | 26 MW |
| 2026-11-02T10:00Z | 29 MW |
| 2026-11-02T11:00Z | 31 MW |
| 2026-11-02T12:00Z | 26 MW |
| 2026-11-02T13:00Z | 31 MW |
| 2026-11-02T14:00Z | 13 MW |
| 2026-11-02T15:00Z | 24 MW |
| 2026-11-02T16:00Z | 22 MW |
| 2026-11-02T17:00Z | 23 MW |
| 2026-11-02T18:00Z | 21 MW |
| 2026-11-02T19:00Z | 17 MW |
| 2026-11-02T20:00Z | 18 MW |
| 2026-11-02T21:00Z | 29 MW |
| 2026-11-02T22:00Z | 22 MW |
| 2026-11-02T23:00Z | 19 MW |
| 2026-11-03T00:00Z | 15 MW |
| 2026-11-03T01:00Z | 0 MW |
| 2026-11-03T02:00Z | 19 MW |
| 2026-11-03T03:00Z | 17 MW |
| 2026-11-03T04:00Z | 13 MW |
| 2026-11-03T05:00Z | 17 MW |
| 2026-11-03T06:00Z | 15 MW |
| 2026-11-03T07:00Z | 15 MW |
| 2026-11-03T08:00Z | 18 MW |
| 2026-11-03T09:00Z | 12 MW |
| 2026-11-03T10:00Z | 24 MW |
| 2026-11-03T11:00Z | 6 MW |
| 2026-11-03T12:00Z | 16 MW |
| 2026-11-03T13:00Z | 11 MW |
| 2026-11-03T14:00Z | 24 MW |
| 2026-11-03T15:00Z | 9 MW |
| 2026-11-03T16:00Z | 24 MW |
| 2026-11-03T17:00Z | 18 MW |
| 2026-11-03T18:00Z | 21 MW |
| 2026-11-03T19:00Z | 11 MW |
| 2026-11-03T20:00Z | 18 MW |
| 2026-11-03T21:00Z | 16 MW |
| 2026-11-03T22:00Z | 18 MW |
| 2026-11-03T23:00Z | 18 MW |
| 2026-11-04T00:00Z | 3 MW |
| 2026-11-04T01:00Z | 22 MW |
| 2026-11-04T02:00Z | 11 MW |
| 2026-11-04T03:00Z | 5 MW |
| 2026-11-04T04:00Z | 17 MW |
| 2026-11-04T05:00Z | 12 MW |
| 2026-11-04T06:00Z | 11 MW |
| 2026-11-04T07:00Z | 21 MW |
| 2026-11-04T08:00Z | 13 MW |
| 2026-11-04T09:00Z | 17 MW |
| 2026-11-04T10:00Z | 8 MW |
| 2026-11-04T11:00Z | 16 MW |
| 2026-11-04T12:00Z | 16 MW |
| 2026-11-04T13:00Z | 7 MW |
| 2026-11-04T14:00Z | 16 MW |
| 2026-11-04T15:00Z | 10 MW |
| 2026-11-04T16:00Z | 13 MW |
| 2026-11-04T17:00Z | 14 MW |
| 2026-11-04T18:00Z | 10 MW |
| 2026-11-04T19:00Z | 20 MW |
| 2026-11-04T20:00Z | 16 MW |
| 2026-11-04T21:00Z | 16 MW |
| 2026-11-04T22:00Z | 6 MW |
| 2026-11-04T23:00Z | 17 MW |
| 2026-11-05T00:00Z | 18 MW |
| 2026-11-05T01:00Z | 14 MW |
| 2026-11-05T02:00Z | 20 MW |
| 2026-11-05T03:00Z | 9 MW |
| 2026-11-05T04:00Z | 18 MW |
| 2026-11-05T05:00Z | 12 MW |
| 2026-11-05T06:00Z | 28 MW |
| 2026-11-05T07:00Z | 12 MW |
| 2026-11-05T08:00Z | 19 MW |
| 2026-11-05T09:00Z | 20 MW |
| 2026-11-05T10:00Z | 15 MW |
| 2026-11-05T11:00Z | 24 MW |
| 2026-11-05T12:00Z | 9 MW |
| 2026-11-05T13:00Z | 9 MW |
| 2026-11-05T14:00Z | n/a |
Show the data table (720 rows)
| Hour starting (UTC) | Hydro |
|---|---|
| 2026-10-06T15:00Z | 7 MW |
| 2026-10-06T16:00Z | 10 MW |
| 2026-10-06T17:00Z | 44 MW |
| 2026-10-06T18:00Z | 73 MW |
| 2026-10-06T19:00Z | 125 MW |
| 2026-10-06T20:00Z | 198 MW |
| 2026-10-06T21:00Z | 668 MW |
| 2026-10-06T22:00Z | 923 MW |
| 2026-10-06T23:00Z | 1,161 MW |
| 2026-10-07T00:00Z | 559 MW |
| 2026-10-07T01:00Z | 64 MW |
| 2026-10-07T02:00Z | 9 MW |
| 2026-10-07T03:00Z | 7 MW |
| 2026-10-07T04:00Z | 7 MW |
| 2026-10-07T05:00Z | 7 MW |
| 2026-10-07T06:00Z | 7 MW |
| 2026-10-07T07:00Z | 7 MW |
| 2026-10-07T08:00Z | 8 MW |
| 2026-10-07T09:00Z | 7 MW |
| 2026-10-07T10:00Z | 7 MW |
| 2026-10-07T11:00Z | 7 MW |
| 2026-10-07T12:00Z | 7 MW |
| 2026-10-07T13:00Z | 7 MW |
| 2026-10-07T14:00Z | 8 MW |
| 2026-10-07T15:00Z | 7 MW |
| 2026-10-07T16:00Z | 8 MW |
| 2026-10-07T17:00Z | 47 MW |
| 2026-10-07T18:00Z | 284 MW |
| 2026-10-07T19:00Z | 418 MW |
| 2026-10-07T20:00Z | 542 MW |
| 2026-10-07T21:00Z | 883 MW |
| 2026-10-07T22:00Z | 1,194 MW |
| 2026-10-07T23:00Z | 1,183 MW |
| 2026-10-08T00:00Z | 685 MW |
| 2026-10-08T01:00Z | 307 MW |
| 2026-10-08T02:00Z | 14 MW |
| 2026-10-08T03:00Z | 9 MW |
| 2026-10-08T04:00Z | 9 MW |
| 2026-10-08T05:00Z | 29 MW |
| 2026-10-08T06:00Z | 30 MW |
| 2026-10-08T07:00Z | 12 MW |
| 2026-10-08T08:00Z | 9 MW |
| 2026-10-08T09:00Z | 10 MW |
| 2026-10-08T10:00Z | 10 MW |
| 2026-10-08T11:00Z | 9 MW |
| 2026-10-08T12:00Z | 9 MW |
| 2026-10-08T13:00Z | 8 MW |
| 2026-10-08T14:00Z | 8 MW |
| 2026-10-08T15:00Z | 7 MW |
| 2026-10-08T16:00Z | 7 MW |
| 2026-10-08T17:00Z | 14 MW |
| 2026-10-08T18:00Z | 194 MW |
| 2026-10-08T19:00Z | 452 MW |
| 2026-10-08T20:00Z | 594 MW |
| 2026-10-08T21:00Z | 1,020 MW |
| 2026-10-08T22:00Z | 1,232 MW |
| 2026-10-08T23:00Z | 1,194 MW |
| 2026-10-09T00:00Z | 706 MW |
| 2026-10-09T01:00Z | 326 MW |
| 2026-10-09T02:00Z | 35 MW |
| 2026-10-09T03:00Z | 27 MW |
| 2026-10-09T04:00Z | 8 MW |
| 2026-10-09T05:00Z | 7 MW |
| 2026-10-09T06:00Z | 8 MW |
| 2026-10-09T07:00Z | 7 MW |
| 2026-10-09T08:00Z | 7 MW |
| 2026-10-09T09:00Z | 7 MW |
| 2026-10-09T10:00Z | 8 MW |
| 2026-10-09T11:00Z | 7 MW |
| 2026-10-09T12:00Z | 7 MW |
| 2026-10-09T13:00Z | 7 MW |
| 2026-10-09T14:00Z | 8 MW |
| 2026-10-09T15:00Z | 7 MW |
| 2026-10-09T16:00Z | 9 MW |
| 2026-10-09T17:00Z | 43 MW |
| 2026-10-09T18:00Z | 73 MW |
| 2026-10-09T19:00Z | 185 MW |
| 2026-10-09T20:00Z | 483 MW |
| 2026-10-09T21:00Z | 1,019 MW |
| 2026-10-09T22:00Z | 1,187 MW |
| 2026-10-09T23:00Z | 1,185 MW |
| 2026-10-10T00:00Z | 805 MW |
| 2026-10-10T01:00Z | 78 MW |
| 2026-10-10T02:00Z | 8 MW |
| 2026-10-10T03:00Z | 8 MW |
| 2026-10-10T04:00Z | 8 MW |
| 2026-10-10T05:00Z | 8 MW |
| 2026-10-10T06:00Z | 8 MW |
| 2026-10-10T07:00Z | 7 MW |
| 2026-10-10T08:00Z | 8 MW |
| 2026-10-10T09:00Z | 8 MW |
| 2026-10-10T10:00Z | 7 MW |
| 2026-10-10T11:00Z | 8 MW |
| 2026-10-10T12:00Z | 8 MW |
| 2026-10-10T13:00Z | 8 MW |
| 2026-10-10T14:00Z | 8 MW |
| 2026-10-10T15:00Z | 8 MW |
| 2026-10-10T16:00Z | 8 MW |
| 2026-10-10T17:00Z | 7 MW |
| 2026-10-10T18:00Z | 11 MW |
| 2026-10-10T19:00Z | 63 MW |
| 2026-10-10T20:00Z | 73 MW |
| 2026-10-10T21:00Z | 332 MW |
| 2026-10-10T22:00Z | 714 MW |
| 2026-10-10T23:00Z | 682 MW |
| 2026-10-11T00:00Z | 184 MW |
| 2026-10-11T01:00Z | 102 MW |
| 2026-10-11T02:00Z | 38 MW |
| 2026-10-11T03:00Z | 36 MW |
| 2026-10-11T04:00Z | 35 MW |
| 2026-10-11T05:00Z | 9 MW |
| 2026-10-11T06:00Z | 8 MW |
| 2026-10-11T07:00Z | 8 MW |
| 2026-10-11T08:00Z | 9 MW |
| 2026-10-11T09:00Z | 8 MW |
| 2026-10-11T10:00Z | 8 MW |
| 2026-10-11T11:00Z | 8 MW |
| 2026-10-11T12:00Z | 8 MW |
| 2026-10-11T13:00Z | 8 MW |
| 2026-10-11T14:00Z | 8 MW |
| 2026-10-11T15:00Z | 8 MW |
| 2026-10-11T16:00Z | 8 MW |
| 2026-10-11T17:00Z | 8 MW |
| 2026-10-11T18:00Z | 8 MW |
| 2026-10-11T19:00Z | 20 MW |
| 2026-10-11T20:00Z | 359 MW |
| 2026-10-11T21:00Z | 588 MW |
| 2026-10-11T22:00Z | 590 MW |
| 2026-10-11T23:00Z | 477 MW |
| 2026-10-12T00:00Z | 46 MW |
| 2026-10-12T01:00Z | 9 MW |
| 2026-10-12T02:00Z | 8 MW |
| 2026-10-12T03:00Z | 9 MW |
| 2026-10-12T04:00Z | 8 MW |
| 2026-10-12T05:00Z | 8 MW |
| 2026-10-12T06:00Z | 8 MW |
| 2026-10-12T07:00Z | 8 MW |
| 2026-10-12T08:00Z | 8 MW |
| 2026-10-12T09:00Z | 8 MW |
| 2026-10-12T10:00Z | 8 MW |
| 2026-10-12T11:00Z | 8 MW |
| 2026-10-12T12:00Z | 8 MW |
| 2026-10-12T13:00Z | 8 MW |
| 2026-10-12T14:00Z | 7 MW |
| 2026-10-12T15:00Z | 8 MW |
| 2026-10-12T16:00Z | 9 MW |
| 2026-10-12T17:00Z | 52 MW |
| 2026-10-12T18:00Z | 80 MW |
| 2026-10-12T19:00Z | 183 MW |
| 2026-10-12T20:00Z | 536 MW |
| 2026-10-12T21:00Z | 1,013 MW |
| 2026-10-12T22:00Z | 1,061 MW |
| 2026-10-12T23:00Z | 1,084 MW |
| 2026-10-13T00:00Z | 625 MW |
| 2026-10-13T01:00Z | 19 MW |
| 2026-10-13T02:00Z | 8 MW |
| 2026-10-13T03:00Z | 8 MW |
| 2026-10-13T04:00Z | 7 MW |
| 2026-10-13T05:00Z | 8 MW |
| 2026-10-13T06:00Z | 8 MW |
| 2026-10-13T07:00Z | 8 MW |
| 2026-10-13T08:00Z | 8 MW |
| 2026-10-13T09:00Z | 8 MW |
| 2026-10-13T10:00Z | 8 MW |
| 2026-10-13T11:00Z | 8 MW |
| 2026-10-13T12:00Z | 8 MW |
| 2026-10-13T13:00Z | 7 MW |
| 2026-10-13T14:00Z | 8 MW |
| 2026-10-13T15:00Z | 9 MW |
| 2026-10-13T16:00Z | 35 MW |
| 2026-10-13T17:00Z | 72 MW |
| 2026-10-13T18:00Z | 187 MW |
| 2026-10-13T19:00Z | 825 MW |
| 2026-10-13T20:00Z | 1,227 MW |
| 2026-10-13T21:00Z | 1,235 MW |
| 2026-10-13T22:00Z | 1,227 MW |
| 2026-10-13T23:00Z | 1,226 MW |
| 2026-10-14T00:00Z | 1,040 MW |
| 2026-10-14T01:00Z | 399 MW |
| 2026-10-14T02:00Z | 47 MW |
| 2026-10-14T03:00Z | 8 MW |
| 2026-10-14T04:00Z | 8 MW |
| 2026-10-14T05:00Z | 8 MW |
| 2026-10-14T06:00Z | 8 MW |
| 2026-10-14T07:00Z | 7 MW |
| 2026-10-14T08:00Z | 8 MW |
| 2026-10-14T09:00Z | 8 MW |
| 2026-10-14T10:00Z | 9 MW |
| 2026-10-14T11:00Z | 23 MW |
| 2026-10-14T12:00Z | 22 MW |
| 2026-10-14T13:00Z | 24 MW |
| 2026-10-14T14:00Z | 27 MW |
| 2026-10-14T15:00Z | 22 MW |
| 2026-10-14T16:00Z | 24 MW |
| 2026-10-14T17:00Z | 61 MW |
| 2026-10-14T18:00Z | 431 MW |
| 2026-10-14T19:00Z | 764 MW |
| 2026-10-14T20:00Z | 913 MW |
| 2026-10-14T21:00Z | 1,167 MW |
| 2026-10-14T22:00Z | 1,169 MW |
| 2026-10-14T23:00Z | 1,155 MW |
| 2026-10-15T00:00Z | 850 MW |
| 2026-10-15T01:00Z | 553 MW |
| 2026-10-15T02:00Z | 143 MW |
| 2026-10-15T03:00Z | 121 MW |
| 2026-10-15T04:00Z | 119 MW |
| 2026-10-15T05:00Z | 51 MW |
| 2026-10-15T06:00Z | 29 MW |
| 2026-10-15T07:00Z | 8 MW |
| 2026-10-15T08:00Z | 8 MW |
| 2026-10-15T09:00Z | 8 MW |
| 2026-10-15T10:00Z | 8 MW |
| 2026-10-15T11:00Z | 8 MW |
| 2026-10-15T12:00Z | 44 MW |
| 2026-10-15T13:00Z | 44 MW |
| 2026-10-15T14:00Z | 46 MW |
| 2026-10-15T15:00Z | 93 MW |
| 2026-10-15T16:00Z | 179 MW |
| 2026-10-15T17:00Z | 320 MW |
| 2026-10-15T18:00Z | 319 MW |
| 2026-10-15T19:00Z | 359 MW |
| 2026-10-15T20:00Z | 562 MW |
| 2026-10-15T21:00Z | 1,033 MW |
| 2026-10-15T22:00Z | 1,157 MW |
| 2026-10-15T23:00Z | 1,130 MW |
| 2026-10-16T00:00Z | 678 MW |
| 2026-10-16T01:00Z | 365 MW |
| 2026-10-16T02:00Z | 265 MW |
| 2026-10-16T03:00Z | 178 MW |
| 2026-10-16T04:00Z | 179 MW |
| 2026-10-16T05:00Z | 177 MW |
| 2026-10-16T06:00Z | 176 MW |
| 2026-10-16T07:00Z | 230 MW |
| 2026-10-16T08:00Z | 283 MW |
| 2026-10-16T09:00Z | 285 MW |
| 2026-10-16T10:00Z | 283 MW |
| 2026-10-16T11:00Z | 310 MW |
| 2026-10-16T12:00Z | 282 MW |
| 2026-10-16T13:00Z | 269 MW |
| 2026-10-16T14:00Z | 272 MW |
| 2026-10-16T15:00Z | 273 MW |
| 2026-10-16T16:00Z | 273 MW |
| 2026-10-16T17:00Z | 271 MW |
| 2026-10-16T18:00Z | 273 MW |
| 2026-10-16T19:00Z | 272 MW |
| 2026-10-16T20:00Z | 273 MW |
| 2026-10-16T21:00Z | 430 MW |
| 2026-10-16T22:00Z | 902 MW |
| 2026-10-16T23:00Z | 871 MW |
| 2026-10-17T00:00Z | 336 MW |
| 2026-10-17T01:00Z | 133 MW |
| 2026-10-17T02:00Z | 20 MW |
| 2026-10-17T03:00Z | 9 MW |
| 2026-10-17T04:00Z | 8 MW |
| 2026-10-17T05:00Z | 8 MW |
| 2026-10-17T06:00Z | 7 MW |
| 2026-10-17T07:00Z | 8 MW |
| 2026-10-17T08:00Z | 8 MW |
| 2026-10-17T09:00Z | 7 MW |
| 2026-10-17T10:00Z | 10 MW |
| 2026-10-17T11:00Z | 105 MW |
| 2026-10-17T12:00Z | 200 MW |
| 2026-10-17T13:00Z | 275 MW |
| 2026-10-17T14:00Z | 268 MW |
| 2026-10-17T15:00Z | 12 MW |
| 2026-10-17T16:00Z | 8 MW |
| 2026-10-17T17:00Z | 8 MW |
| 2026-10-17T18:00Z | 8 MW |
| 2026-10-17T19:00Z | 8 MW |
| 2026-10-17T20:00Z | 13 MW |
| 2026-10-17T21:00Z | 181 MW |
| 2026-10-17T22:00Z | 542 MW |
| 2026-10-17T23:00Z | 446 MW |
| 2026-10-18T00:00Z | 75 MW |
| 2026-10-18T01:00Z | 10 MW |
| 2026-10-18T02:00Z | 8 MW |
| 2026-10-18T03:00Z | 8 MW |
| 2026-10-18T04:00Z | 7 MW |
| 2026-10-18T05:00Z | 8 MW |
| 2026-10-18T06:00Z | 8 MW |
| 2026-10-18T07:00Z | 8 MW |
| 2026-10-18T08:00Z | 8 MW |
| 2026-10-18T09:00Z | 7 MW |
| 2026-10-18T10:00Z | 8 MW |
| 2026-10-18T11:00Z | 12 MW |
| 2026-10-18T12:00Z | 112 MW |
| 2026-10-18T13:00Z | 114 MW |
| 2026-10-18T14:00Z | 10 MW |
| 2026-10-18T15:00Z | 8 MW |
| 2026-10-18T16:00Z | 8 MW |
| 2026-10-18T17:00Z | 8 MW |
| 2026-10-18T18:00Z | 8 MW |
| 2026-10-18T19:00Z | 9 MW |
| 2026-10-18T20:00Z | 19 MW |
| 2026-10-18T21:00Z | 315 MW |
| 2026-10-18T22:00Z | 348 MW |
| 2026-10-18T23:00Z | 338 MW |
| 2026-10-19T00:00Z | 82 MW |
| 2026-10-19T01:00Z | 9 MW |
| 2026-10-19T02:00Z | 7 MW |
| 2026-10-19T03:00Z | 8 MW |
| 2026-10-19T04:00Z | 8 MW |
| 2026-10-19T05:00Z | 7 MW |
| 2026-10-19T06:00Z | 8 MW |
| 2026-10-19T07:00Z | 7 MW |
| 2026-10-19T08:00Z | 8 MW |
| 2026-10-19T09:00Z | 8 MW |
| 2026-10-19T10:00Z | 11 MW |
| 2026-10-19T11:00Z | 128 MW |
| 2026-10-19T12:00Z | 382 MW |
| 2026-10-19T13:00Z | 284 MW |
| 2026-10-19T14:00Z | 18 MW |
| 2026-10-19T15:00Z | 8 MW |
| 2026-10-19T16:00Z | 8 MW |
| 2026-10-19T17:00Z | 41 MW |
| 2026-10-19T18:00Z | 57 MW |
| 2026-10-19T19:00Z | 113 MW |
| 2026-10-19T20:00Z | 172 MW |
| 2026-10-19T21:00Z | 345 MW |
| 2026-10-19T22:00Z | 917 MW |
| 2026-10-19T23:00Z | 849 MW |
| 2026-10-20T00:00Z | 203 MW |
| 2026-10-20T01:00Z | 30 MW |
| 2026-10-20T02:00Z | 8 MW |
| 2026-10-20T03:00Z | 8 MW |
| 2026-10-20T04:00Z | 7 MW |
| 2026-10-20T05:00Z | 7 MW |
| 2026-10-20T06:00Z | 7 MW |
| 2026-10-20T07:00Z | 8 MW |
| 2026-10-20T08:00Z | 8 MW |
| 2026-10-20T09:00Z | 7 MW |
| 2026-10-20T10:00Z | 16 MW |
| 2026-10-20T11:00Z | 207 MW |
| 2026-10-20T12:00Z | 210 MW |
| 2026-10-20T13:00Z | 71 MW |
| 2026-10-20T14:00Z | 42 MW |
| 2026-10-20T15:00Z | 44 MW |
| 2026-10-20T16:00Z | 45 MW |
| 2026-10-20T17:00Z | 65 MW |
| 2026-10-20T18:00Z | 91 MW |
| 2026-10-20T19:00Z | 127 MW |
| 2026-10-20T20:00Z | 214 MW |
| 2026-10-20T21:00Z | 741 MW |
| 2026-10-20T22:00Z | 1,028 MW |
| 2026-10-20T23:00Z | 853 MW |
| 2026-10-21T00:00Z | 340 MW |
| 2026-10-21T01:00Z | 218 MW |
| 2026-10-21T02:00Z | 158 MW |
| 2026-10-21T03:00Z | 11 MW |
| 2026-10-21T04:00Z | 7 MW |
| 2026-10-21T05:00Z | 8 MW |
| 2026-10-21T06:00Z | 7 MW |
| 2026-10-21T07:00Z | 8 MW |
| 2026-10-21T08:00Z | 7 MW |
| 2026-10-21T09:00Z | 7 MW |
| 2026-10-21T10:00Z | 8 MW |
| 2026-10-21T11:00Z | 7 MW |
| 2026-10-21T12:00Z | 9 MW |
| 2026-10-21T13:00Z | 40 MW |
| 2026-10-21T14:00Z | 44 MW |
| 2026-10-21T15:00Z | 90 MW |
| 2026-10-21T16:00Z | 92 MW |
| 2026-10-21T17:00Z | 122 MW |
| 2026-10-21T18:00Z | 349 MW |
| 2026-10-21T19:00Z | 410 MW |
| 2026-10-21T20:00Z | 730 MW |
| 2026-10-21T21:00Z | 797 MW |
| 2026-10-21T22:00Z | 1,185 MW |
| 2026-10-21T23:00Z | 1,186 MW |
| 2026-10-22T00:00Z | 756 MW |
| 2026-10-22T01:00Z | 158 MW |
| 2026-10-22T02:00Z | 44 MW |
| 2026-10-22T03:00Z | 43 MW |
| 2026-10-22T04:00Z | 43 MW |
| 2026-10-22T05:00Z | 42 MW |
| 2026-10-22T06:00Z | 43 MW |
| 2026-10-22T07:00Z | 43 MW |
| 2026-10-22T08:00Z | 43 MW |
| 2026-10-22T09:00Z | 42 MW |
| 2026-10-22T10:00Z | 43 MW |
| 2026-10-22T11:00Z | 42 MW |
| 2026-10-22T12:00Z | 41 MW |
| 2026-10-22T13:00Z | 43 MW |
| 2026-10-22T14:00Z | 43 MW |
| 2026-10-22T15:00Z | 44 MW |
| 2026-10-22T16:00Z | 91 MW |
| 2026-10-22T17:00Z | 163 MW |
| 2026-10-22T18:00Z | 244 MW |
| 2026-10-22T19:00Z | 275 MW |
| 2026-10-22T20:00Z | 363 MW |
| 2026-10-22T21:00Z | 670 MW |
| 2026-10-22T22:00Z | 1,178 MW |
| 2026-10-22T23:00Z | 1,185 MW |
| 2026-10-23T00:00Z | 671 MW |
| 2026-10-23T01:00Z | 295 MW |
| 2026-10-23T02:00Z | 253 MW |
| 2026-10-23T03:00Z | 137 MW |
| 2026-10-23T04:00Z | 136 MW |
| 2026-10-23T05:00Z | 62 MW |
| 2026-10-23T06:00Z | 9 MW |
| 2026-10-23T07:00Z | 8 MW |
| 2026-10-23T08:00Z | 8 MW |
| 2026-10-23T09:00Z | 7 MW |
| 2026-10-23T10:00Z | 8 MW |
| 2026-10-23T11:00Z | 8 MW |
| 2026-10-23T12:00Z | 8 MW |
| 2026-10-23T13:00Z | 7 MW |
| 2026-10-23T14:00Z | 8 MW |
| 2026-10-23T15:00Z | 8 MW |
| 2026-10-23T16:00Z | 10 MW |
| 2026-10-23T17:00Z | 48 MW |
| 2026-10-23T18:00Z | 73 MW |
| 2026-10-23T19:00Z | 173 MW |
| 2026-10-23T20:00Z | 335 MW |
| 2026-10-23T21:00Z | 538 MW |
| 2026-10-23T22:00Z | 1,086 MW |
| 2026-10-23T23:00Z | 1,178 MW |
| 2026-10-24T00:00Z | 340 MW |
| 2026-10-24T01:00Z | 173 MW |
| 2026-10-24T02:00Z | 116 MW |
| 2026-10-24T03:00Z | 117 MW |
| 2026-10-24T04:00Z | 86 MW |
| 2026-10-24T05:00Z | 7 MW |
| 2026-10-24T06:00Z | 7 MW |
| 2026-10-24T07:00Z | 8 MW |
| 2026-10-24T08:00Z | 7 MW |
| 2026-10-24T09:00Z | 8 MW |
| 2026-10-24T10:00Z | 8 MW |
| 2026-10-24T11:00Z | 12 MW |
| 2026-10-24T12:00Z | 16 MW |
| 2026-10-24T13:00Z | 18 MW |
| 2026-10-24T14:00Z | 17 MW |
| 2026-10-24T15:00Z | 18 MW |
| 2026-10-24T16:00Z | 17 MW |
| 2026-10-24T17:00Z | 16 MW |
| 2026-10-24T18:00Z | 18 MW |
| 2026-10-24T19:00Z | 20 MW |
| 2026-10-24T20:00Z | 94 MW |
| 2026-10-24T21:00Z | 220 MW |
| 2026-10-24T22:00Z | 857 MW |
| 2026-10-24T23:00Z | 845 MW |
| 2026-10-25T00:00Z | 210 MW |
| 2026-10-25T01:00Z | 172 MW |
| 2026-10-25T02:00Z | 102 MW |
| 2026-10-25T03:00Z | 79 MW |
| 2026-10-25T04:00Z | 9 MW |
| 2026-10-25T05:00Z | 7 MW |
| 2026-10-25T06:00Z | 7 MW |
| 2026-10-25T07:00Z | 7 MW |
| 2026-10-25T08:00Z | 7 MW |
| 2026-10-25T09:00Z | 7 MW |
| 2026-10-25T10:00Z | 7 MW |
| 2026-10-25T11:00Z | 7 MW |
| 2026-10-25T12:00Z | 7 MW |
| 2026-10-25T13:00Z | 6 MW |
| 2026-10-25T14:00Z | 7 MW |
| 2026-10-25T15:00Z | 7 MW |
| 2026-10-25T16:00Z | 7 MW |
| 2026-10-25T17:00Z | 7 MW |
| 2026-10-25T18:00Z | 68 MW |
| 2026-10-25T19:00Z | 78 MW |
| 2026-10-25T20:00Z | 103 MW |
| 2026-10-25T21:00Z | 339 MW |
| 2026-10-25T22:00Z | 979 MW |
| 2026-10-25T23:00Z | 787 MW |
| 2026-10-26T00:00Z | 194 MW |
| 2026-10-26T01:00Z | 10 MW |
| 2026-10-26T02:00Z | 7 MW |
| 2026-10-26T03:00Z | 6 MW |
| 2026-10-26T04:00Z | 7 MW |
| 2026-10-26T05:00Z | 7 MW |
| 2026-10-26T06:00Z | 6 MW |
| 2026-10-26T07:00Z | 7 MW |
| 2026-10-26T08:00Z | 7 MW |
| 2026-10-26T09:00Z | 7 MW |
| 2026-10-26T10:00Z | 8 MW |
| 2026-10-26T11:00Z | 7 MW |
| 2026-10-26T12:00Z | 7 MW |
| 2026-10-26T13:00Z | 28 MW |
| 2026-10-26T14:00Z | 28 MW |
| 2026-10-26T15:00Z | 28 MW |
| 2026-10-26T16:00Z | 9 MW |
| 2026-10-26T17:00Z | 45 MW |
| 2026-10-26T18:00Z | 79 MW |
| 2026-10-26T19:00Z | 141 MW |
| 2026-10-26T20:00Z | 452 MW |
| 2026-10-26T21:00Z | 696 MW |
| 2026-10-26T22:00Z | 1,171 MW |
| 2026-10-26T23:00Z | 1,168 MW |
| 2026-10-27T00:00Z | 643 MW |
| 2026-10-27T01:00Z | 47 MW |
| 2026-10-27T02:00Z | 28 MW |
| 2026-10-27T03:00Z | 28 MW |
| 2026-10-27T04:00Z | 8 MW |
| 2026-10-27T05:00Z | 8 MW |
| 2026-10-27T06:00Z | 7 MW |
| 2026-10-27T07:00Z | 8 MW |
| 2026-10-27T08:00Z | 8 MW |
| 2026-10-27T09:00Z | 8 MW |
| 2026-10-27T10:00Z | 11 MW |
| 2026-10-27T11:00Z | 141 MW |
| 2026-10-27T12:00Z | 141 MW |
| 2026-10-27T13:00Z | 143 MW |
| 2026-10-27T14:00Z | 163 MW |
| 2026-10-27T15:00Z | 164 MW |
| 2026-10-27T16:00Z | 220 MW |
| 2026-10-27T17:00Z | 266 MW |
| 2026-10-27T18:00Z | 267 MW |
| 2026-10-27T19:00Z | 265 MW |
| 2026-10-27T20:00Z | 273 MW |
| 2026-10-27T21:00Z | 353 MW |
| 2026-10-27T22:00Z | 1,050 MW |
| 2026-10-27T23:00Z | 1,001 MW |
| 2026-10-28T00:00Z | 461 MW |
| 2026-10-28T01:00Z | 127 MW |
| 2026-10-28T02:00Z | 97 MW |
| 2026-10-28T03:00Z | 11 MW |
| 2026-10-28T04:00Z | 8 MW |
| 2026-10-28T05:00Z | 8 MW |
| 2026-10-28T06:00Z | 7 MW |
| 2026-10-28T07:00Z | 8 MW |
| 2026-10-28T08:00Z | 8 MW |
| 2026-10-28T09:00Z | 8 MW |
| 2026-10-28T10:00Z | 11 MW |
| 2026-10-28T11:00Z | 141 MW |
| 2026-10-28T12:00Z | 141 MW |
| 2026-10-28T13:00Z | 143 MW |
| 2026-10-28T14:00Z | 163 MW |
| 2026-10-28T15:00Z | 164 MW |
| 2026-10-28T16:00Z | 220 MW |
| 2026-10-28T17:00Z | 266 MW |
| 2026-10-28T18:00Z | 267 MW |
| 2026-10-28T19:00Z | 265 MW |
| 2026-10-28T20:00Z | 273 MW |
| 2026-10-28T21:00Z | 353 MW |
| 2026-10-28T22:00Z | 1,050 MW |
| 2026-10-28T23:00Z | 1,001 MW |
| 2026-10-29T00:00Z | 461 MW |
| 2026-10-29T01:00Z | 127 MW |
| 2026-10-29T02:00Z | 97 MW |
| 2026-10-29T03:00Z | 11 MW |
| 2026-10-29T04:00Z | 8 MW |
| 2026-10-29T05:00Z | n/a |
| 2026-10-29T06:00Z | n/a |
| 2026-10-29T07:00Z | n/a |
| 2026-10-29T08:00Z | n/a |
| 2026-10-29T09:00Z | n/a |
| 2026-10-29T10:00Z | n/a |
| 2026-10-29T11:00Z | n/a |
| 2026-10-29T12:00Z | n/a |
| 2026-10-29T13:00Z | 85 MW |
| 2026-10-29T14:00Z | 101 MW |
| 2026-10-29T15:00Z | 103 MW |
| 2026-10-29T16:00Z | 143 MW |
| 2026-10-29T17:00Z | 227 MW |
| 2026-10-29T18:00Z | 309 MW |
| 2026-10-29T19:00Z | 460 MW |
| 2026-10-29T20:00Z | 525 MW |
| 2026-10-29T21:00Z | 930 MW |
| 2026-10-29T22:00Z | 1,142 MW |
| 2026-10-29T23:00Z | 1,076 MW |
| 2026-10-30T00:00Z | 454 MW |
| 2026-10-30T01:00Z | 159 MW |
| 2026-10-30T02:00Z | 149 MW |
| 2026-10-30T03:00Z | 40 MW |
| 2026-10-30T04:00Z | 65 MW |
| 2026-10-30T05:00Z | 68 MW |
| 2026-10-30T06:00Z | 65 MW |
| 2026-10-30T07:00Z | 10 MW |
| 2026-10-30T08:00Z | 9 MW |
| 2026-10-30T09:00Z | 42 MW |
| 2026-10-30T10:00Z | 42 MW |
| 2026-10-30T11:00Z | 43 MW |
| 2026-10-30T12:00Z | 43 MW |
| 2026-10-30T13:00Z | 44 MW |
| 2026-10-30T14:00Z | 76 MW |
| 2026-10-30T15:00Z | 86 MW |
| 2026-10-30T16:00Z | 97 MW |
| 2026-10-30T17:00Z | 98 MW |
| 2026-10-30T18:00Z | 135 MW |
| 2026-10-30T19:00Z | 171 MW |
| 2026-10-30T20:00Z | 235 MW |
| 2026-10-30T21:00Z | 307 MW |
| 2026-10-30T22:00Z | 650 MW |
| 2026-10-30T23:00Z | 602 MW |
| 2026-10-31T00:00Z | 187 MW |
| 2026-10-31T01:00Z | 113 MW |
| 2026-10-31T02:00Z | 112 MW |
| 2026-10-31T03:00Z | 78 MW |
| 2026-10-31T04:00Z | 78 MW |
| 2026-10-31T05:00Z | 78 MW |
| 2026-10-31T06:00Z | 76 MW |
| 2026-10-31T07:00Z | 9 MW |
| 2026-10-31T08:00Z | 8 MW |
| 2026-10-31T09:00Z | 7 MW |
| 2026-10-31T10:00Z | 8 MW |
| 2026-10-31T11:00Z | 7 MW |
| 2026-10-31T12:00Z | 8 MW |
| 2026-10-31T13:00Z | 10 MW |
| 2026-10-31T14:00Z | 62 MW |
| 2026-10-31T15:00Z | 65 MW |
| 2026-10-31T16:00Z | 116 MW |
| 2026-10-31T17:00Z | 117 MW |
| 2026-10-31T18:00Z | 138 MW |
| 2026-10-31T19:00Z | 158 MW |
| 2026-10-31T20:00Z | 158 MW |
| 2026-10-31T21:00Z | 144 MW |
| 2026-10-31T22:00Z | 333 MW |
| 2026-10-31T23:00Z | 287 MW |
| 2026-11-01T00:00Z | 34 MW |
| 2026-11-01T01:00Z | 8 MW |
| 2026-11-01T02:00Z | 8 MW |
| 2026-11-01T03:00Z | 8 MW |
| 2026-11-01T04:00Z | 7 MW |
| 2026-11-01T05:00Z | 8 MW |
| 2026-11-01T06:00Z | 8 MW |
| 2026-11-01T07:00Z | 8 MW |
| 2026-11-01T08:00Z | 8 MW |
| 2026-11-01T09:00Z | 8 MW |
| 2026-11-01T10:00Z | 8 MW |
| 2026-11-01T11:00Z | 8 MW |
| 2026-11-01T12:00Z | 18 MW |
| 2026-11-01T13:00Z | 18 MW |
| 2026-11-01T14:00Z | 73 MW |
| 2026-11-01T15:00Z | 107 MW |
| 2026-11-01T16:00Z | 110 MW |
| 2026-11-01T17:00Z | 169 MW |
| 2026-11-01T18:00Z | 171 MW |
| 2026-11-01T19:00Z | 182 MW |
| 2026-11-01T20:00Z | 206 MW |
| 2026-11-01T21:00Z | 249 MW |
| 2026-11-01T22:00Z | 361 MW |
| 2026-11-01T23:00Z | 362 MW |
| 2026-11-02T00:00Z | 312 MW |
| 2026-11-02T01:00Z | 52 MW |
| 2026-11-02T02:00Z | 23 MW |
| 2026-11-02T03:00Z | 10 MW |
| 2026-11-02T04:00Z | 7 MW |
| 2026-11-02T05:00Z | 8 MW |
| 2026-11-02T06:00Z | 8 MW |
| 2026-11-02T07:00Z | 8 MW |
| 2026-11-02T08:00Z | 8 MW |
| 2026-11-02T09:00Z | 7 MW |
| 2026-11-02T10:00Z | 8 MW |
| 2026-11-02T11:00Z | 9 MW |
| 2026-11-02T12:00Z | 21 MW |
| 2026-11-02T13:00Z | 153 MW |
| 2026-11-02T14:00Z | 135 MW |
| 2026-11-02T15:00Z | 11 MW |
| 2026-11-02T16:00Z | 8 MW |
| 2026-11-02T17:00Z | 11 MW |
| 2026-11-02T18:00Z | 130 MW |
| 2026-11-02T19:00Z | 152 MW |
| 2026-11-02T20:00Z | 153 MW |
| 2026-11-02T21:00Z | 239 MW |
| 2026-11-02T22:00Z | 929 MW |
| 2026-11-02T23:00Z | 842 MW |
| 2026-11-03T00:00Z | 681 MW |
| 2026-11-03T01:00Z | 392 MW |
| 2026-11-03T02:00Z | 149 MW |
| 2026-11-03T03:00Z | 10 MW |
| 2026-11-03T04:00Z | 6 MW |
| 2026-11-03T05:00Z | 7 MW |
| 2026-11-03T06:00Z | 7 MW |
| 2026-11-03T07:00Z | 6 MW |
| 2026-11-03T08:00Z | 7 MW |
| 2026-11-03T09:00Z | 7 MW |
| 2026-11-03T10:00Z | 7 MW |
| 2026-11-03T11:00Z | 7 MW |
| 2026-11-03T12:00Z | 29 MW |
| 2026-11-03T13:00Z | 147 MW |
| 2026-11-03T14:00Z | 149 MW |
| 2026-11-03T15:00Z | 107 MW |
| 2026-11-03T16:00Z | 112 MW |
| 2026-11-03T17:00Z | 120 MW |
| 2026-11-03T18:00Z | 137 MW |
| 2026-11-03T19:00Z | 172 MW |
| 2026-11-03T20:00Z | 173 MW |
| 2026-11-03T21:00Z | 215 MW |
| 2026-11-03T22:00Z | 221 MW |
| 2026-11-03T23:00Z | 452 MW |
| 2026-11-04T00:00Z | 513 MW |
| 2026-11-04T01:00Z | 382 MW |
| 2026-11-04T02:00Z | 233 MW |
| 2026-11-04T03:00Z | 41 MW |
| 2026-11-04T04:00Z | 7 MW |
| 2026-11-04T05:00Z | 7 MW |
| 2026-11-04T06:00Z | 6 MW |
| 2026-11-04T07:00Z | 7 MW |
| 2026-11-04T08:00Z | 6 MW |
| 2026-11-04T09:00Z | 7 MW |
| 2026-11-04T10:00Z | 6 MW |
| 2026-11-04T11:00Z | 7 MW |
| 2026-11-04T12:00Z | 11 MW |
| 2026-11-04T13:00Z | 152 MW |
| 2026-11-04T14:00Z | 138 MW |
| 2026-11-04T15:00Z | 45 MW |
| 2026-11-04T16:00Z | 76 MW |
| 2026-11-04T17:00Z | 80 MW |
| 2026-11-04T18:00Z | 132 MW |
| 2026-11-04T19:00Z | 142 MW |
| 2026-11-04T20:00Z | 141 MW |
| 2026-11-04T21:00Z | 154 MW |
| 2026-11-04T22:00Z | 525 MW |
| 2026-11-04T23:00Z | 764 MW |
| 2026-11-05T00:00Z | 515 MW |
| 2026-11-05T01:00Z | 285 MW |
| 2026-11-05T02:00Z | 144 MW |
| 2026-11-05T03:00Z | 10 MW |
| 2026-11-05T04:00Z | 8 MW |
| 2026-11-05T05:00Z | n/a |
| 2026-11-05T06:00Z | n/a |
| 2026-11-05T07:00Z | n/a |
| 2026-11-05T08:00Z | n/a |
| 2026-11-05T09:00Z | n/a |
| 2026-11-05T10:00Z | n/a |
| 2026-11-05T11:00Z | n/a |
| 2026-11-05T12:00Z | n/a |
| 2026-11-05T13:00Z | n/a |
| 2026-11-05T14:00Z | n/a |
Source: U.S. Energy Information Administration (EIA). (US Government work, public domain) Data as of 2026-11-05T14:00Z.
Day by Day
Daily totals, Central time dates, through 2026-11-04Show the data table (400 rows)
| Date (Central time) | Demand |
|---|---|
| 2025-10-01 | 467 MWh |
| 2025-10-02 | 487 MWh |
| 2025-10-03 | 464 MWh |
| 2025-10-04 | 538 MWh |
| 2025-10-05 | 472 MWh |
| 2025-10-06 | 405 MWh |
| 2025-10-07 | 355 MWh |
| 2025-10-08 | 355 MWh |
| 2025-10-09 | 425 MWh |
| 2025-10-10 | 471 MWh |
| 2025-10-11 | 333 MWh |
| 2025-10-12 | 503 MWh |
| 2025-10-13 | 377 MWh |
| 2025-10-14 | 381 MWh |
| 2025-10-15 | 483 MWh |
| 2025-10-16 | 574 MWh |
| 2025-10-17 | 481 MWh |
| 2025-10-18 | 412 MWh |
| 2025-10-19 | 435 MWh |
| 2025-10-20 | 507 MWh |
| 2025-10-21 | 401 MWh |
| 2025-10-22 | 379 MWh |
| 2025-10-23 | 375 MWh |
| 2025-10-24 | 400 MWh |
| 2025-10-25 | 389 MWh |
| 2025-10-26 | 350 MWh |
| 2025-10-27 | 345 MWh |
| 2025-10-28 | 401 MWh |
| 2025-10-29 | 458 MWh |
| 2025-10-30 | 447 MWh |
| 2025-10-31 | 311 MWh |
| 2025-11-01 | 375 MWh |
| 2025-11-02 | 335 MWh |
| 2025-11-03 | n/a |
| 2025-11-04 | 521 MWh |
| 2025-11-05 | 496 MWh |
| 2025-11-06 | n/a |
| 2025-11-07 | n/a |
| 2025-11-08 | n/a |
| 2025-11-09 | n/a |
| 2025-11-10 | n/a |
| 2025-11-11 | 504 MWh |
| 2025-11-12 | 410 MWh |
| 2025-11-13 | n/a |
| 2025-11-14 | n/a |
| 2025-11-15 | n/a |
| 2025-11-16 | n/a |
| 2025-11-17 | n/a |
| 2025-11-18 | n/a |
| 2025-11-19 | n/a |
| 2025-11-20 | n/a |
| 2025-11-21 | n/a |
| 2025-11-22 | n/a |
| 2025-11-23 | n/a |
| 2025-11-24 | n/a |
| 2025-11-25 | n/a |
| 2025-11-26 | n/a |
| 2025-11-27 | n/a |
| 2025-11-28 | n/a |
| 2025-11-29 | n/a |
| 2025-11-30 | 467 MWh |
| 2025-12-01 | n/a |
| 2025-12-02 | n/a |
| 2025-12-03 | n/a |
| 2025-12-04 | n/a |
| 2025-12-05 | n/a |
| 2025-12-06 | n/a |
| 2025-12-07 | n/a |
| 2025-12-08 | n/a |
| 2025-12-09 | n/a |
| 2025-12-10 | n/a |
| 2025-12-11 | 536 MWh |
| 2025-12-12 | 425 MWh |
| 2025-12-13 | 562 MWh |
| 2025-12-14 | 591 MWh |
| 2025-12-15 | 659 MWh |
| 2025-12-16 | 600 MWh |
| 2025-12-17 | 568 MWh |
| 2025-12-18 | 572 MWh |
| 2025-12-19 | 626 MWh |
| 2025-12-20 | 622 MWh |
| 2025-12-21 | n/a |
| 2025-12-22 | n/a |
| 2025-12-23 | n/a |
| 2025-12-24 | n/a |
| 2025-12-25 | n/a |
| 2025-12-26 | n/a |
| 2025-12-27 | n/a |
| 2025-12-28 | n/a |
| 2025-12-29 | n/a |
| 2025-12-30 | n/a |
| 2025-12-31 | n/a |
| 2026-01-01 | 498 MWh |
| 2026-01-02 | 509 MWh |
| 2026-01-03 | 533 MWh |
| 2026-01-04 | 642 MWh |
| 2026-01-05 | 573 MWh |
| 2026-01-06 | 415 MWh |
| 2026-01-07 | 596 MWh |
| 2026-01-08 | 683 MWh |
| 2026-01-09 | 491 MWh |
| 2026-01-10 | 662 MWh |
| 2026-01-11 | 527 MWh |
| 2026-01-12 | 638 MWh |
| 2026-01-13 | 573 MWh |
| 2026-01-14 | 629 MWh |
| 2026-01-15 | 552 MWh |
| 2026-01-16 | 673 MWh |
| 2026-01-17 | 543 MWh |
| 2026-01-18 | 490 MWh |
| 2026-01-19 | 710 MWh |
| 2026-01-20 | 612 MWh |
| 2026-01-21 | 556 MWh |
| 2026-01-22 | 521 MWh |
| 2026-01-23 | 800 MWh |
| 2026-01-24 | 790 MWh |
| 2026-01-25 | 743 MWh |
| 2026-01-26 | 702 MWh |
| 2026-01-27 | 641 MWh |
| 2026-01-28 | 578 MWh |
| 2026-01-29 | 769 MWh |
| 2026-01-30 | 778 MWh |
| 2026-01-31 | 765 MWh |
| 2026-02-01 | 946 MWh |
| 2026-02-02 | 876 MWh |
| 2026-02-03 | 820 MWh |
| 2026-02-04 | 616 MWh |
| 2026-02-05 | 609 MWh |
| 2026-02-06 | 608 MWh |
| 2026-02-07 | 665 MWh |
| 2026-02-08 | 650 MWh |
| 2026-02-09 | 652 MWh |
| 2026-02-10 | 781 MWh |
| 2026-02-11 | 530 MWh |
| 2026-02-12 | 653 MWh |
| 2026-02-13 | 833 MWh |
| 2026-02-14 | 571 MWh |
| 2026-02-15 | 598 MWh |
| 2026-02-16 | 709 MWh |
| 2026-02-17 | 713 MWh |
| 2026-02-18 | 637 MWh |
| 2026-02-19 | 711 MWh |
| 2026-02-20 | 568 MWh |
| 2026-02-21 | 588 MWh |
| 2026-02-22 | 620 MWh |
| 2026-02-23 | 649 MWh |
| 2026-02-24 | 754 MWh |
| 2026-02-25 | 589 MWh |
| 2026-02-26 | 517 MWh |
| 2026-02-27 | 481 MWh |
| 2026-02-28 | 542 MWh |
| 2026-03-01 | 552 MWh |
| 2026-03-02 | 635 MWh |
| 2026-03-03 | 644 MWh |
| 2026-03-04 | 522 MWh |
| 2026-03-05 | 558 MWh |
| 2026-03-06 | 698 MWh |
| 2026-03-07 | 543 MWh |
| 2026-03-08 | 585 MWh |
| 2026-03-09 | 664 MWh |
| 2026-03-10 | 684 MWh |
| 2026-03-11 | 588 MWh |
| 2026-03-12 | 623 MWh |
| 2026-03-13 | 532 MWh |
| 2026-03-14 | 430 MWh |
| 2026-03-15 | 560 MWh |
| 2026-03-16 | 546 MWh |
| 2026-03-17 | 595 MWh |
| 2026-03-18 | 537 MWh |
| 2026-03-19 | 484 MWh |
| 2026-03-20 | 469 MWh |
| 2026-03-21 | 425 MWh |
| 2026-03-22 | 586 MWh |
| 2026-03-23 | 525 MWh |
| 2026-03-24 | 442 MWh |
| 2026-03-25 | 549 MWh |
| 2026-03-26 | 578 MWh |
| 2026-03-27 | 568 MWh |
| 2026-03-28 | 435 MWh |
| 2026-03-29 | 601 MWh |
| 2026-03-30 | 623 MWh |
| 2026-03-31 | 566 MWh |
| 2026-04-01 | 416 MWh |
| 2026-04-02 | 606 MWh |
| 2026-04-03 | 671 MWh |
| 2026-04-04 | 706 MWh |
| 2026-04-05 | 470 MWh |
| 2026-04-06 | 572 MWh |
| 2026-04-07 | 521 MWh |
| 2026-04-08 | 490 MWh |
| 2026-04-09 | 531 MWh |
| 2026-04-10 | 505 MWh |
| 2026-04-11 | 607 MWh |
| 2026-04-12 | 711 MWh |
| 2026-04-13 | 786 MWh |
| 2026-04-14 | 684 MWh |
| 2026-04-15 | 579 MWh |
| 2026-04-16 | 573 MWh |
| 2026-04-17 | 788 MWh |
| 2026-04-18 | 707 MWh |
| 2026-04-19 | 628 MWh |
| 2026-04-20 | 648 MWh |
| 2026-04-21 | 533 MWh |
| 2026-04-22 | 573 MWh |
| 2026-04-23 | 567 MWh |
| 2026-04-24 | 455 MWh |
| 2026-04-25 | 498 MWh |
| 2026-04-26 | 438 MWh |
| 2026-04-27 | 471 MWh |
| 2026-04-28 | 543 MWh |
| 2026-04-29 | 524 MWh |
| 2026-04-30 | 484 MWh |
| 2026-05-01 | 527 MWh |
| 2026-05-02 | 503 MWh |
| 2026-05-03 | 517 MWh |
| 2026-05-04 | 657 MWh |
| 2026-05-05 | 589 MWh |
| 2026-05-06 | 660 MWh |
| 2026-05-07 | 584 MWh |
| 2026-05-08 | 664 MWh |
| 2026-05-09 | 533 MWh |
| 2026-05-10 | 549 MWh |
| 2026-05-11 | 537 MWh |
| 2026-05-12 | 615 MWh |
| 2026-05-13 | 529 MWh |
| 2026-05-14 | 603 MWh |
| 2026-05-15 | 654 MWh |
| 2026-05-16 | 638 MWh |
| 2026-05-17 | 606 MWh |
| 2026-05-18 | 568 MWh |
| 2026-05-19 | 426 MWh |
| 2026-05-20 | n/a |
| 2026-05-21 | n/a |
| 2026-05-22 | n/a |
| 2026-05-23 | n/a |
| 2026-05-24 | 559 MWh |
| 2026-05-25 | 629 MWh |
| 2026-05-26 | 600 MWh |
| 2026-05-27 | 708 MWh |
| 2026-05-28 | 571 MWh |
| 2026-05-29 | 599 MWh |
| 2026-05-30 | 649 MWh |
| 2026-05-31 | 671 MWh |
| 2026-06-01 | 622 MWh |
| 2026-06-02 | 637 MWh |
| 2026-06-03 | 604 MWh |
| 2026-06-04 | 648 MWh |
| 2026-06-05 | 607 MWh |
| 2026-06-06 | 469 MWh |
| 2026-06-07 | 524 MWh |
| 2026-06-08 | 569 MWh |
| 2026-06-09 | 640 MWh |
| 2026-06-10 | 693 MWh |
| 2026-06-11 | 661 MWh |
| 2026-06-12 | 607 MWh |
| 2026-06-13 | 581 MWh |
| 2026-06-14 | 513 MWh |
| 2026-06-15 | 480 MWh |
| 2026-06-16 | 572 MWh |
| 2026-06-17 | 626 MWh |
| 2026-06-18 | 618 MWh |
| 2026-06-19 | 549 MWh |
| 2026-06-20 | 524 MWh |
| 2026-06-21 | 491 MWh |
| 2026-06-22 | 656 MWh |
| 2026-06-23 | 456 MWh |
| 2026-06-24 | 457 MWh |
| 2026-06-25 | 585 MWh |
| 2026-06-26 | 521 MWh |
| 2026-06-27 | 650 MWh |
| 2026-06-28 | 729 MWh |
| 2026-06-29 | 753 MWh |
| 2026-06-30 | 658 MWh |
| 2026-07-01 | 729 MWh |
| 2026-07-02 | 717 MWh |
| 2026-07-03 | 656 MWh |
| 2026-07-04 | 603 MWh |
| 2026-07-05 | 525 MWh |
| 2026-07-06 | 581 MWh |
| 2026-07-07 | 572 MWh |
| 2026-07-08 | 594 MWh |
| 2026-07-09 | 609 MWh |
| 2026-07-10 | 628 MWh |
| 2026-07-11 | 527 MWh |
| 2026-07-12 | 586 MWh |
| 2026-07-13 | 537 MWh |
| 2026-07-14 | 542 MWh |
| 2026-07-15 | 537 MWh |
| 2026-07-16 | 603 MWh |
| 2026-07-17 | 652 MWh |
| 2026-07-18 | 659 MWh |
| 2026-07-19 | 634 MWh |
| 2026-07-20 | 585 MWh |
| 2026-07-21 | 614 MWh |
| 2026-07-22 | 298 MWh |
| 2026-07-23 | 287 MWh |
| 2026-07-24 | 562 MWh |
| 2026-07-25 | 748 MWh |
| 2026-07-26 | 848 MWh |
| 2026-07-27 | 854 MWh |
| 2026-07-28 | 802 MWh |
| 2026-07-29 | 659 MWh |
| 2026-07-30 | 635 MWh |
| 2026-07-31 | 597 MWh |
| 2026-08-01 | 552 MWh |
| 2026-08-02 | 512 MWh |
| 2026-08-03 | 597 MWh |
| 2026-08-04 | 570 MWh |
| 2026-08-05 | 557 MWh |
| 2026-08-06 | 598 MWh |
| 2026-08-07 | 667 MWh |
| 2026-08-08 | 527 MWh |
| 2026-08-09 | 691 MWh |
| 2026-08-10 | 686 MWh |
| 2026-08-11 | 762 MWh |
| 2026-08-12 | 808 MWh |
| 2026-08-13 | 866 MWh |
| 2026-08-14 | 795 MWh |
| 2026-08-15 | 778 MWh |
| 2026-08-16 | 653 MWh |
| 2026-08-17 | 567 MWh |
| 2026-08-18 | 632 MWh |
| 2026-08-19 | 664 MWh |
| 2026-08-20 | 568 MWh |
| 2026-08-21 | 649 MWh |
| 2026-08-22 | 549 MWh |
| 2026-08-23 | 507 MWh |
| 2026-08-24 | 576 MWh |
| 2026-08-25 | 570 MWh |
| 2026-08-26 | 502 MWh |
| 2026-08-27 | 491 MWh |
| 2026-08-28 | 427 MWh |
| 2026-08-29 | 572 MWh |
| 2026-08-30 | 646 MWh |
| 2026-08-31 | 665 MWh |
| 2026-09-01 | 692 MWh |
| 2026-09-02 | 741 MWh |
| 2026-09-03 | 722 MWh |
| 2026-09-04 | 677 MWh |
| 2026-09-05 | 576 MWh |
| 2026-09-06 | 499 MWh |
| 2026-09-07 | 506 MWh |
| 2026-09-08 | 636 MWh |
| 2026-09-09 | 630 MWh |
| 2026-09-10 | 550 MWh |
| 2026-09-11 | 526 MWh |
| 2026-09-12 | 532 MWh |
| 2026-09-13 | 518 MWh |
| 2026-09-14 | 562 MWh |
| 2026-09-15 | 584 MWh |
| 2026-09-16 | 509 MWh |
| 2026-09-17 | 537 MWh |
| 2026-09-18 | 531 MWh |
| 2026-09-19 | 550 MWh |
| 2026-09-20 | 418 MWh |
| 2026-09-21 | 411 MWh |
| 2026-09-22 | 450 MWh |
| 2026-09-23 | 415 MWh |
| 2026-09-24 | 413 MWh |
| 2026-09-25 | 409 MWh |
| 2026-09-26 | 398 MWh |
| 2026-09-27 | 416 MWh |
| 2026-09-28 | 380 MWh |
| 2026-09-29 | 434 MWh |
| 2026-09-30 | 497 MWh |
| 2026-10-01 | 328 MWh |
| 2026-10-02 | 305 MWh |
| 2026-10-03 | 279 MWh |
| 2026-10-04 | 294 MWh |
| 2026-10-05 | 280 MWh |
| 2026-10-06 | 359 MWh |
| 2026-10-07 | 420 MWh |
| 2026-10-08 | 411 MWh |
| 2026-10-09 | 392 MWh |
| 2026-10-10 | 513 MWh |
| 2026-10-11 | 464 MWh |
| 2026-10-12 | 525 MWh |
| 2026-10-13 | 537 MWh |
| 2026-10-14 | 586 MWh |
| 2026-10-15 | 596 MWh |
| 2026-10-16 | 633 MWh |
| 2026-10-17 | 377 MWh |
| 2026-10-18 | 498 MWh |
| 2026-10-19 | 459 MWh |
| 2026-10-20 | 341 MWh |
| 2026-10-21 | 318 MWh |
| 2026-10-22 | 263 MWh |
| 2026-10-23 | 311 MWh |
| 2026-10-24 | 316 MWh |
| 2026-10-25 | 316 MWh |
| 2026-10-26 | 350 MWh |
| 2026-10-27 | 368 MWh |
| 2026-10-28 | 453 MWh |
| 2026-10-29 | 393 MWh |
| 2026-10-30 | 377 MWh |
| 2026-10-31 | 353 MWh |
| 2026-11-01 | 335 MWh |
| 2026-11-02 | 492 MWh |
| 2026-11-03 | 364 MWh |
| 2026-11-04 | 338 MWh |
Source: U.S. Energy Information Administration (EIA). (US Government work, public domain) Data as of 2026-11-04. Daily totals are EIA's own daily aggregation in the balancing authority's reporting time zone.
Year by Year
Summed from EIA daily operator data| Year | Demand | Net generation | Largest source | Days reported |
|---|---|---|---|---|
| 2026 (partial) | 174 GWh | 3.10 TWh | Hydro 100.0% | 308 |
| 2025 (partial) | 164 GWh | 4.79 TWh | Hydro 100.0% | 319 |
| 2024 | 197 GWh | 3.85 TWh | Hydro 56.6% | 366 |
| 2023 | 410 GWh | 4.27 TWh | Hydro 85.6% | 365 |
| 2022 (partial) | 563 GWh | 5.86 TWh | Hydro 74.4% | 359 |
| 2021 | 574 GWh | 7.42 TWh | Hydro 76.9% | 365 |
| 2020 | 598 GWh | 8.05 TWh | Hydro 79.6% | 366 |
| 2019 | 655 GWh | 8.60 TWh | Hydro 81.1% | 365 |
A year is partial when EIA has not published every day; 2024 is the latest complete year. Operator totals differ slightly from annual statistics, which are compiled later from plant surveys.
Source: U.S. Energy Information Administration (EIA). (US Government work, public domain) Data as of 2026-11-04.
Records
From EIA operator data held by World Power Monitor| Record | Value | When |
|---|---|---|
| Highest daily demand, 2019 onward | 2.80 GWh | 2021-02-15 (15 February 2021) |
| Highest hourly demand since 2026-06-16 (16 June 2026) | 59 MW | 17 Jun 2026, 11:00 CDT (UTC-05:00) |
| Highest solar share of a day's generation, 2019 onward | 100.0% | 2024-06-03 (3 June 2024) |
| Highest wind share of a day's generation, 2019 onward | 100.0% | 2024-06-03 (3 June 2024) |
Source: U.S. Energy Information Administration (EIA). (US Government work, public domain) Data as of 2026-11-04.
Power Flows With Neighbours
Net totals, 2026-10-06 (6 October 2026) to 2026-11-04 (4 November 2026)| Neighbour | Direction | Net energy |
|---|---|---|
| SPP | SPA exports | 92.7 GWh |
| SIKE | SPA imports | 53.9 GWh |
| AECI | SPA exports | 47.7 GWh |
| MISO | SPA exports | 30.3 GWh |
Source: U.S. Energy Information Administration (EIA). (US Government work, public domain) Data as of 2026-11-04.
Share and Embed
Figures as of 2026-11-05 (5 November 2026)Download share image (PNG, 1200 x 630 pixels) with the latest demand and largest source for SPA, credited to EIA. The image is rebuilt with the page. More about grid widgets.
Embed this widget
Free to use on your own site. Keep the source line in the frame; it carries the data licence and a link back here.
The frame reports its height to the page with postMessage type wpm-embed-height if you want it to resize.
Related
Cite this page
World Power Monitor. (2026). SPA Electricity Demand and Generation Mix. https://worldpowermonitor.com/zones/spa/
World Power Monitor. SPA Electricity Demand and Generation Mix. Data as of 2026-11-05 13:00 UTC. Data from U.S. Energy Information Administration. https://worldpowermonitor.com/zones/spa/
@misc{wpm_zones_spa_2026,
title = {{SPA Electricity Demand and Generation Mix}},
author = {{World Power Monitor}},
year = {2026},
note = {Data as of 2026-11-05 13:00 UTC. Data from U.S. Energy Information Administration.},