Ireland and Northern Ireland (SEM) Electricity Demand and Generation Mix
Wind was the largest source in the hour starting 28 Oct 2026, 08:00 GMT (UTC+00:00), at 57% of generation. Operator data is hourly and provisional, and may be revised.
Key Facts
- Ireland and Northern Ireland (SEM) is a bidding zone of the European electricity market, with one wholesale price per market interval.
- Wind supplied 56.8% of Ireland and Northern Ireland (SEM)'s generation in the hour starting 28 Oct 2026, 08:00 GMT (UTC+00:00).
- The day-ahead price in Ireland and Northern Ireland (SEM) averaged EUR 132.93/MWh for delivery on 2026-10-27 (27 October 2026).
- Installed generating capacity in Ireland and Northern Ireland (SEM) was 12.7 GW in 2024, as reported to ENTSO-E.
Generation by Source
Latest hour with generation by source: 28 Oct 2026, 08:00 GMT (UTC+00:00)| Source | Output | Share |
|---|---|---|
| Wind | 2,078 MW | 56.8% |
| Gas | 1,286 MW | 35.2% |
| Storage | 143 MW | 3.9% |
| Other fossil | 80 MW | 2.2% |
| Hydro | 72 MW | 2.0% |
| Solar | 0 MW | 0.0% |
| Oil | -5 MW | own use |
| Coal | -7 MW | own use |
| Total from these sources | 3,659 MW |
Generation by production type is published separately from load, so this hour can differ from the latest load hour. Negative storage values are pumping or charging.
Other is shown as Ireland and Northern Ireland (SEM) reports it: the platform has published zero for every day since 19 November 2025 (the last non zero daily total was on 18 November 2025). We have not changed or filled the figure, and cannot tell from the data whether the source stopped generating or stopped reporting. All flagged series.
Source: ENTSO-E Transparency Platform (transparency.entsoe.eu), CC BY 4.0. Aggregated and converted by World Power Monitor; ENTSO-E does not endorse this site. (ENTSO-E Terms of Use plus CC BY 4.0 for listed data items) Data as of 2026-10-28T08:00:00Z.
Day-Ahead Price
Delivery day 2026-10-27 (27 October 2026), local timePrices are in EUR per MWh as published, not converted. Full price history for Ireland and Northern Ireland (SEM) and day-ahead prices in every bidding zone.
Source: ENTSO-E Transparency Platform (transparency.entsoe.eu), CC BY 4.0. Aggregated and converted by World Power Monitor; ENTSO-E does not endorse this site. (ENTSO-E Terms of Use plus CC BY 4.0 for listed data items) Data as of 2026-10-27.
Last 30 Days, Hourly
Times in UTCShow the data table (720 rows)
| Hour starting (UTC) | Wind | Gas | Oil | Other fossil | Storage |
|---|---|---|---|---|---|
| 2026-09-28T11:00Z | n/a | n/a | n/a | -1 MW | 20 MW |
| 2026-09-28T12:00Z | n/a | n/a | n/a | -1 MW | 20 MW |
| 2026-09-28T13:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-09-28T14:00Z | n/a | n/a | n/a | -1 MW | -217 MW |
| 2026-09-28T15:00Z | 1,767 MW | n/a | n/a | -1 MW | -179 MW |
| 2026-09-28T16:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-09-28T17:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-09-28T18:00Z | 2,324 MW | 1,512 MW | 427 MW | -1 MW | 233 MW |
| 2026-09-28T19:00Z | 2,791 MW | n/a | n/a | -1 MW | 134 MW |
| 2026-09-28T20:00Z | n/a | n/a | n/a | -1 MW | 19 MW |
| 2026-09-28T21:00Z | n/a | n/a | n/a | -1 MW | 15 MW |
| 2026-09-28T22:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-09-28T23:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-09-29T00:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-09-29T01:00Z | n/a | n/a | n/a | -1 MW | -220 MW |
| 2026-09-29T02:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-09-29T03:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-09-29T04:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-09-29T05:00Z | n/a | n/a | n/a | -1 MW | 22 MW |
| 2026-09-29T06:00Z | n/a | n/a | n/a | -1 MW | 25 MW |
| 2026-09-29T07:00Z | 3,841 MW | 626 MW | 166 MW | -1 MW | 21 MW |
| 2026-09-29T08:00Z | n/a | n/a | n/a | -1 MW | 23 MW |
| 2026-09-29T09:00Z | 3,774 MW | 615 MW | 164 MW | -1 MW | 20 MW |
| 2026-09-29T10:00Z | 3,851 MW | 545 MW | 165 MW | -1 MW | 21 MW |
| 2026-09-29T11:00Z | 3,868 MW | 528 MW | 164 MW | -1 MW | 20 MW |
| 2026-09-29T12:00Z | 3,900 MW | 559 MW | 171 MW | -1 MW | 25 MW |
| 2026-09-29T13:00Z | 3,855 MW | 556 MW | 169 MW | -1 MW | 23 MW |
| 2026-09-29T14:00Z | 3,773 MW | 575 MW | 219 MW | -1 MW | 29 MW |
| 2026-09-29T15:00Z | 3,600 MW | 595 MW | 430 MW | -1 MW | 25 MW |
| 2026-09-29T16:00Z | 3,564 MW | 770 MW | 427 MW | -1 MW | 23 MW |
| 2026-09-29T17:00Z | 3,662 MW | 761 MW | 343 MW | -1 MW | 40 MW |
| 2026-09-29T18:00Z | 3,757 MW | 793 MW | 244 MW | -1 MW | 24 MW |
| 2026-09-29T19:00Z | 3,608 MW | 763 MW | 221 MW | -3 MW | 60 MW |
| 2026-09-29T20:00Z | 3,370 MW | 640 MW | 199 MW | -3 MW | 39 MW |
| 2026-09-29T21:00Z | 3,128 MW | 530 MW | 166 MW | -3 MW | 20 MW |
| 2026-09-29T22:00Z | 2,980 MW | 517 MW | 164 MW | -4 MW | 20 MW |
| 2026-09-29T23:00Z | 2,629 MW | 522 MW | 165 MW | -4 MW | 18 MW |
| 2026-09-30T00:00Z | 2,474 MW | 552 MW | 166 MW | -4 MW | -153 MW |
| 2026-09-30T01:00Z | 2,683 MW | 553 MW | 166 MW | -4 MW | -224 MW |
| 2026-09-30T02:00Z | 2,776 MW | 567 MW | 169 MW | -4 MW | -222 MW |
| 2026-09-30T03:00Z | 2,672 MW | 558 MW | 166 MW | -4 MW | -220 MW |
| 2026-09-30T04:00Z | 2,725 MW | 553 MW | 165 MW | -4 MW | -217 MW |
| 2026-09-30T05:00Z | 2,887 MW | 576 MW | 171 MW | -5 MW | -215 MW |
| 2026-09-30T06:00Z | 2,945 MW | 632 MW | 226 MW | -5 MW | -94 MW |
| 2026-09-30T07:00Z | 3,100 MW | 621 MW | 166 MW | -6 MW | 22 MW |
| 2026-09-30T08:00Z | 3,216 MW | 586 MW | 165 MW | -6 MW | 21 MW |
| 2026-09-30T09:00Z | 3,080 MW | 527 MW | 165 MW | -5 MW | 21 MW |
| 2026-09-30T10:00Z | 3,024 MW | 540 MW | 167 MW | -6 MW | 23 MW |
| 2026-09-30T11:00Z | 2,931 MW | 561 MW | 173 MW | -6 MW | 28 MW |
| 2026-09-30T12:00Z | 2,807 MW | 526 MW | 164 MW | -7 MW | 21 MW |
| 2026-09-30T13:00Z | 2,813 MW | 529 MW | 166 MW | -7 MW | 21 MW |
| 2026-09-30T14:00Z | 2,689 MW | 551 MW | 171 MW | -7 MW | 24 MW |
| 2026-09-30T15:00Z | 2,760 MW | 686 MW | 177 MW | -8 MW | 29 MW |
| 2026-09-30T16:00Z | 2,592 MW | 1,320 MW | 277 MW | -8 MW | 158 MW |
| 2026-09-30T17:00Z | 2,442 MW | 1,324 MW | 296 MW | 25 MW | 224 MW |
| 2026-09-30T18:00Z | 2,368 MW | 1,025 MW | 248 MW | 41 MW | 262 MW |
| 2026-09-30T19:00Z | 2,233 MW | 1,030 MW | 200 MW | 41 MW | 141 MW |
| 2026-09-30T20:00Z | 2,172 MW | 974 MW | 182 MW | 41 MW | 0 MW |
| 2026-09-30T21:00Z | n/a | n/a | n/a | 41 MW | 0 MW |
| 2026-09-30T22:00Z | 2,203 MW | 633 MW | 177 MW | 41 MW | -113 MW |
| 2026-09-30T23:00Z | 2,150 MW | 621 MW | 168 MW | 41 MW | -189 MW |
| 2026-10-01T00:00Z | 1,960 MW | 622 MW | 170 MW | 41 MW | -225 MW |
| 2026-10-01T01:00Z | 1,912 MW | 658 MW | 164 MW | 41 MW | -224 MW |
| 2026-10-01T02:00Z | 2,100 MW | 700 MW | 169 MW | 41 MW | -221 MW |
| 2026-10-01T03:00Z | 2,048 MW | 644 MW | 164 MW | 41 MW | -220 MW |
| 2026-10-01T04:00Z | 2,165 MW | 552 MW | 164 MW | 41 MW | -217 MW |
| 2026-10-01T05:00Z | 2,156 MW | 639 MW | 172 MW | 41 MW | -143 MW |
| 2026-10-01T06:00Z | 2,257 MW | 728 MW | 164 MW | 41 MW | 31 MW |
| 2026-10-01T07:00Z | 2,063 MW | 767 MW | 164 MW | 41 MW | 37 MW |
| 2026-10-01T08:00Z | 1,738 MW | 755 MW | 165 MW | 41 MW | 10 MW |
| 2026-10-01T09:00Z | 1,571 MW | 570 MW | 164 MW | 41 MW | 10 MW |
| 2026-10-01T10:00Z | 1,744 MW | 567 MW | 175 MW | 41 MW | 12 MW |
| 2026-10-01T11:00Z | 2,115 MW | 425 MW | 175 MW | 41 MW | 13 MW |
| 2026-10-01T12:00Z | 2,594 MW | 463 MW | 172 MW | 41 MW | 33 MW |
| 2026-10-01T13:00Z | 2,814 MW | 469 MW | 173 MW | 41 MW | -35 MW |
| 2026-10-01T14:00Z | 2,980 MW | 659 MW | 185 MW | 41 MW | 0 MW |
| 2026-10-01T15:00Z | 2,945 MW | 894 MW | 238 MW | 41 MW | 29 MW |
| 2026-10-01T16:00Z | 2,880 MW | 991 MW | 444 MW | 41 MW | 171 MW |
| 2026-10-01T17:00Z | 2,897 MW | 1,001 MW | 431 MW | 41 MW | 285 MW |
| 2026-10-01T18:00Z | 2,960 MW | 1,010 MW | 434 MW | 41 MW | 192 MW |
| 2026-10-01T19:00Z | 2,937 MW | 982 MW | 426 MW | 41 MW | 96 MW |
| 2026-10-01T20:00Z | 2,766 MW | 873 MW | 273 MW | 41 MW | 9 MW |
| 2026-10-01T21:00Z | 2,506 MW | 882 MW | 297 MW | 41 MW | 0 MW |
| 2026-10-01T22:00Z | 2,338 MW | 842 MW | 281 MW | 41 MW | -75 MW |
| 2026-10-01T23:00Z | 2,183 MW | 880 MW | 198 MW | 41 MW | -226 MW |
| 2026-10-02T00:00Z | 2,074 MW | 930 MW | 180 MW | 41 MW | -225 MW |
| 2026-10-02T01:00Z | 2,077 MW | 869 MW | 164 MW | 41 MW | -224 MW |
| 2026-10-02T02:00Z | 2,194 MW | 797 MW | 164 MW | 41 MW | -221 MW |
| 2026-10-02T03:00Z | 2,363 MW | 774 MW | 171 MW | 41 MW | -217 MW |
| 2026-10-02T04:00Z | 2,456 MW | 803 MW | 164 MW | 41 MW | -217 MW |
| 2026-10-02T05:00Z | 2,554 MW | 798 MW | 169 MW | 41 MW | -106 MW |
| 2026-10-02T06:00Z | 2,680 MW | 934 MW | 164 MW | 41 MW | 55 MW |
| 2026-10-02T07:00Z | 2,996 MW | 831 MW | 170 MW | 41 MW | 13 MW |
| 2026-10-02T08:00Z | 3,268 MW | 738 MW | 170 MW | 41 MW | 8 MW |
| 2026-10-02T09:00Z | 3,405 MW | 473 MW | 164 MW | 41 MW | 6 MW |
| 2026-10-02T10:00Z | 3,571 MW | 415 MW | 177 MW | 41 MW | 28 MW |
| 2026-10-02T11:00Z | 3,637 MW | 565 MW | 176 MW | 41 MW | 29 MW |
| 2026-10-02T12:00Z | 3,306 MW | 621 MW | 172 MW | 41 MW | 17 MW |
| 2026-10-02T13:00Z | 3,315 MW | 570 MW | 173 MW | 41 MW | 13 MW |
| 2026-10-02T14:00Z | 3,298 MW | 633 MW | 164 MW | 41 MW | 10 MW |
| 2026-10-02T15:00Z | 3,020 MW | 845 MW | 170 MW | 41 MW | 12 MW |
| 2026-10-02T16:00Z | 2,465 MW | 1,097 MW | 210 MW | 49 MW | 45 MW |
| 2026-10-02T17:00Z | 1,910 MW | 1,238 MW | 219 MW | 65 MW | 79 MW |
| 2026-10-02T18:00Z | 1,648 MW | 1,255 MW | 187 MW | 98 MW | 183 MW |
| 2026-10-02T19:00Z | 1,362 MW | 1,263 MW | 191 MW | 98 MW | 287 MW |
| 2026-10-02T20:00Z | 1,274 MW | 1,168 MW | 171 MW | 98 MW | 158 MW |
| 2026-10-02T21:00Z | 1,184 MW | 1,157 MW | 211 MW | 98 MW | 0 MW |
| 2026-10-02T22:00Z | n/a | n/a | n/a | 101 MW | -2 MW |
| 2026-10-02T23:00Z | 845 MW | 1,387 MW | 314 MW | 100 MW | -189 MW |
| 2026-10-03T00:00Z | 755 MW | 1,397 MW | 329 MW | 99 MW | -225 MW |
| 2026-10-03T01:00Z | 664 MW | 1,412 MW | 319 MW | 99 MW | -223 MW |
| 2026-10-03T02:00Z | 586 MW | 1,484 MW | 353 MW | 101 MW | -220 MW |
| 2026-10-03T03:00Z | 453 MW | 1,488 MW | 348 MW | 101 MW | -218 MW |
| 2026-10-03T04:00Z | 506 MW | 1,462 MW | 350 MW | 100 MW | -217 MW |
| 2026-10-03T05:00Z | 593 MW | 1,410 MW | 308 MW | 99 MW | -215 MW |
| 2026-10-03T06:00Z | n/a | n/a | n/a | 100 MW | -35 MW |
| 2026-10-03T07:00Z | 502 MW | 1,370 MW | 182 MW | 100 MW | 103 MW |
| 2026-10-03T08:00Z | 336 MW | 1,401 MW | 288 MW | 100 MW | 132 MW |
| 2026-10-03T09:00Z | 338 MW | 1,458 MW | 304 MW | 100 MW | 0 MW |
| 2026-10-03T10:00Z | 353 MW | 1,268 MW | 168 MW | 97 MW | 0 MW |
| 2026-10-03T11:00Z | 378 MW | 963 MW | 166 MW | 100 MW | 0 MW |
| 2026-10-03T12:00Z | 341 MW | 885 MW | 170 MW | 100 MW | 0 MW |
| 2026-10-03T13:00Z | 370 MW | 858 MW | 165 MW | 99 MW | 0 MW |
| 2026-10-03T14:00Z | 444 MW | 885 MW | 173 MW | 101 MW | 0 MW |
| 2026-10-03T15:00Z | 521 MW | 992 MW | 170 MW | 100 MW | 0 MW |
| 2026-10-03T16:00Z | 660 MW | 1,248 MW | 173 MW | 80 MW | 68 MW |
| 2026-10-03T17:00Z | 806 MW | 1,335 MW | 215 MW | 80 MW | 237 MW |
| 2026-10-03T18:00Z | 1,059 MW | 1,223 MW | 165 MW | 80 MW | 130 MW |
| 2026-10-03T19:00Z | 1,178 MW | 1,294 MW | 164 MW | 80 MW | 15 MW |
| 2026-10-03T20:00Z | 1,418 MW | 1,146 MW | 165 MW | 80 MW | 9 MW |
| 2026-10-03T21:00Z | 1,588 MW | 1,192 MW | 173 MW | 80 MW | 3 MW |
| 2026-10-03T22:00Z | 1,764 MW | 1,066 MW | 165 MW | 80 MW | 0 MW |
| 2026-10-03T23:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-04T00:00Z | 1,848 MW | 1,122 MW | 179 MW | 80 MW | -73 MW |
| 2026-10-04T01:00Z | 1,857 MW | 1,103 MW | 170 MW | 80 MW | -74 MW |
| 2026-10-04T02:00Z | 1,838 MW | 1,109 MW | 173 MW | 80 MW | -73 MW |
| 2026-10-04T03:00Z | 1,883 MW | 1,093 MW | 170 MW | 80 MW | -73 MW |
| 2026-10-04T04:00Z | 1,890 MW | 1,110 MW | 165 MW | 80 MW | -73 MW |
| 2026-10-04T05:00Z | 2,033 MW | 1,061 MW | 176 MW | 80 MW | -72 MW |
| 2026-10-04T06:00Z | 1,858 MW | 1,013 MW | 164 MW | 80 MW | 0 MW |
| 2026-10-04T07:00Z | 1,798 MW | 801 MW | 172 MW | 80 MW | 0 MW |
| 2026-10-04T08:00Z | 1,755 MW | 693 MW | 167 MW | 80 MW | 0 MW |
| 2026-10-04T09:00Z | 1,767 MW | 568 MW | 80 MW | 80 MW | 6 MW |
| 2026-10-04T10:00Z | 1,808 MW | 582 MW | -5 MW | 80 MW | 13 MW |
| 2026-10-04T11:00Z | 1,849 MW | 635 MW | -5 MW | 80 MW | -111 MW |
| 2026-10-04T12:00Z | 1,853 MW | 671 MW | -5 MW | 80 MW | -148 MW |
| 2026-10-04T13:00Z | 2,108 MW | 648 MW | -5 MW | 57 MW | -146 MW |
| 2026-10-04T14:00Z | 2,693 MW | 627 MW | 54 MW | 53 MW | -109 MW |
| 2026-10-04T15:00Z | 2,914 MW | 688 MW | 198 MW | 55 MW | 61 MW |
| 2026-10-04T16:00Z | 2,816 MW | 872 MW | 258 MW | 55 MW | 183 MW |
| 2026-10-04T17:00Z | 2,672 MW | 971 MW | 192 MW | 55 MW | 245 MW |
| 2026-10-04T18:00Z | 2,464 MW | 1,092 MW | 238 MW | 55 MW | 236 MW |
| 2026-10-04T19:00Z | 2,570 MW | 1,096 MW | 336 MW | 55 MW | 233 MW |
| 2026-10-04T20:00Z | 2,790 MW | 997 MW | 215 MW | 55 MW | 15 MW |
| 2026-10-04T21:00Z | 2,692 MW | 705 MW | 164 MW | 55 MW | 2 MW |
| 2026-10-04T22:00Z | 2,601 MW | 652 MW | 167 MW | 55 MW | -150 MW |
| 2026-10-04T23:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-05T00:00Z | 2,398 MW | 545 MW | 165 MW | 55 MW | -222 MW |
| 2026-10-05T01:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-05T02:00Z | 2,322 MW | 559 MW | 168 MW | 55 MW | -217 MW |
| 2026-10-05T03:00Z | 2,287 MW | 567 MW | 170 MW | 55 MW | -214 MW |
| 2026-10-05T04:00Z | 2,500 MW | 566 MW | 170 MW | 55 MW | -177 MW |
| 2026-10-05T05:00Z | 2,738 MW | 715 MW | 172 MW | 55 MW | 0 MW |
| 2026-10-05T06:00Z | 2,576 MW | 1,123 MW | 191 MW | 55 MW | 0 MW |
| 2026-10-05T07:00Z | 2,374 MW | 1,114 MW | 178 MW | 55 MW | 20 MW |
| 2026-10-05T08:00Z | 2,237 MW | 1,013 MW | 164 MW | 55 MW | 21 MW |
| 2026-10-05T09:00Z | 2,087 MW | 729 MW | 173 MW | 55 MW | 26 MW |
| 2026-10-05T10:00Z | 2,006 MW | 667 MW | 175 MW | 55 MW | 0 MW |
| 2026-10-05T11:00Z | 1,811 MW | 612 MW | 174 MW | 55 MW | -72 MW |
| 2026-10-05T12:00Z | 1,517 MW | n/a | 173 MW | 55 MW | -72 MW |
| 2026-10-05T13:00Z | 1,260 MW | 658 MW | 164 MW | 55 MW | 3 MW |
| 2026-10-05T14:00Z | 1,026 MW | 1,002 MW | 174 MW | 55 MW | 13 MW |
| 2026-10-05T15:00Z | 861 MW | 1,399 MW | 236 MW | -6 MW | 79 MW |
| 2026-10-05T16:00Z | 685 MW | 1,470 MW | 325 MW | 14 MW | 161 MW |
| 2026-10-05T17:00Z | 511 MW | 1,433 MW | 362 MW | 55 MW | 218 MW |
| 2026-10-05T18:00Z | 435 MW | 1,481 MW | 376 MW | 55 MW | 252 MW |
| 2026-10-05T19:00Z | 354 MW | 1,449 MW | 374 MW | 55 MW | 236 MW |
| 2026-10-05T20:00Z | 291 MW | 1,439 MW | 385 MW | 55 MW | 42 MW |
| 2026-10-05T21:00Z | 252 MW | 1,407 MW | 369 MW | 55 MW | 5 MW |
| 2026-10-05T22:00Z | 241 MW | 1,438 MW | 320 MW | 55 MW | -189 MW |
| 2026-10-05T23:00Z | 265 MW | 1,390 MW | 301 MW | 55 MW | -225 MW |
| 2026-10-06T00:00Z | 282 MW | 1,311 MW | 303 MW | 55 MW | -223 MW |
| 2026-10-06T01:00Z | 244 MW | 1,353 MW | 300 MW | 55 MW | -220 MW |
| 2026-10-06T02:00Z | 263 MW | 1,354 MW | 302 MW | 55 MW | -219 MW |
| 2026-10-06T03:00Z | 361 MW | 1,273 MW | 256 MW | 55 MW | -218 MW |
| 2026-10-06T04:00Z | 377 MW | 1,318 MW | 164 MW | 55 MW | -215 MW |
| 2026-10-06T05:00Z | 400 MW | 1,396 MW | 197 MW | 55 MW | -70 MW |
| 2026-10-06T06:00Z | 415 MW | 1,502 MW | 346 MW | 55 MW | 58 MW |
| 2026-10-06T07:00Z | 409 MW | 1,548 MW | 355 MW | 55 MW | 44 MW |
| 2026-10-06T08:00Z | 311 MW | 1,565 MW | 351 MW | 55 MW | 13 MW |
| 2026-10-06T09:00Z | 285 MW | 1,500 MW | 323 MW | 55 MW | 11 MW |
| 2026-10-06T10:00Z | 339 MW | 1,450 MW | 297 MW | 55 MW | 3 MW |
| 2026-10-06T11:00Z | 429 MW | 1,433 MW | 285 MW | 55 MW | 0 MW |
| 2026-10-06T12:00Z | 517 MW | 1,375 MW | 272 MW | 55 MW | 0 MW |
| 2026-10-06T13:00Z | 535 MW | 1,369 MW | 260 MW | 55 MW | 0 MW |
| 2026-10-06T14:00Z | 635 MW | 1,377 MW | 261 MW | 55 MW | 0 MW |
| 2026-10-06T15:00Z | 676 MW | 1,465 MW | 283 MW | 55 MW | 11 MW |
| 2026-10-06T16:00Z | 713 MW | 1,562 MW | 360 MW | 55 MW | 79 MW |
| 2026-10-06T17:00Z | 688 MW | 1,570 MW | 379 MW | 63 MW | 179 MW |
| 2026-10-06T18:00Z | 769 MW | 1,534 MW | 346 MW | 67 MW | 242 MW |
| 2026-10-06T19:00Z | 753 MW | 1,464 MW | 341 MW | 66 MW | 172 MW |
| 2026-10-06T20:00Z | 899 MW | 1,382 MW | 292 MW | 68 MW | 98 MW |
| 2026-10-06T21:00Z | 957 MW | 1,347 MW | 247 MW | 69 MW | 41 MW |
| 2026-10-06T22:00Z | 952 MW | 1,392 MW | 240 MW | 68 MW | -113 MW |
| 2026-10-06T23:00Z | 974 MW | 1,226 MW | 164 MW | 68 MW | -188 MW |
| 2026-10-07T00:00Z | 982 MW | 1,241 MW | 176 MW | 71 MW | -147 MW |
| 2026-10-07T01:00Z | n/a | n/a | n/a | 69 MW | -146 MW |
| 2026-10-07T02:00Z | 914 MW | 1,243 MW | 170 MW | 70 MW | -145 MW |
| 2026-10-07T03:00Z | 1,096 MW | 1,180 MW | 179 MW | 72 MW | -144 MW |
| 2026-10-07T04:00Z | n/a | n/a | n/a | 70 MW | -144 MW |
| 2026-10-07T05:00Z | 1,264 MW | 1,276 MW | 177 MW | 71 MW | -68 MW |
| 2026-10-07T06:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-07T07:00Z | 1,206 MW | 1,261 MW | 195 MW | 70 MW | 179 MW |
| 2026-10-07T08:00Z | 1,162 MW | 1,398 MW | 197 MW | 69 MW | 13 MW |
| 2026-10-07T09:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-07T10:00Z | 1,786 MW | 923 MW | 164 MW | 67 MW | 8 MW |
| 2026-10-07T11:00Z | 1,955 MW | 826 MW | 164 MW | 41 MW | -73 MW |
| 2026-10-07T12:00Z | 2,323 MW | 845 MW | 172 MW | 41 MW | -145 MW |
| 2026-10-07T13:00Z | 2,535 MW | 868 MW | 184 MW | 41 MW | -143 MW |
| 2026-10-07T14:00Z | 2,567 MW | 847 MW | 172 MW | 100 MW | -71 MW |
| 2026-10-07T15:00Z | 2,684 MW | 859 MW | 178 MW | 41 MW | 55 MW |
| 2026-10-07T16:00Z | 2,837 MW | 914 MW | 187 MW | 41 MW | 123 MW |
| 2026-10-07T17:00Z | 2,456 MW | 1,210 MW | 330 MW | 63 MW | 195 MW |
| 2026-10-07T18:00Z | 2,326 MW | 1,147 MW | 241 MW | 74 MW | 177 MW |
| 2026-10-07T19:00Z | 2,155 MW | 1,041 MW | 165 MW | 67 MW | 104 MW |
| 2026-10-07T20:00Z | 2,088 MW | 1,034 MW | -5 MW | 69 MW | 0 MW |
| 2026-10-07T21:00Z | 1,729 MW | 1,086 MW | -5 MW | 75 MW | 0 MW |
| 2026-10-07T22:00Z | 1,384 MW | 1,182 MW | -5 MW | 77 MW | -78 MW |
| 2026-10-07T23:00Z | 1,315 MW | 1,271 MW | -5 MW | 82 MW | -222 MW |
| 2026-10-08T00:00Z | 1,018 MW | 1,298 MW | -4 MW | 79 MW | -222 MW |
| 2026-10-08T01:00Z | 805 MW | 1,452 MW | -3 MW | 79 MW | -220 MW |
| 2026-10-08T02:00Z | 723 MW | 1,502 MW | -3 MW | 80 MW | -218 MW |
| 2026-10-08T03:00Z | 669 MW | 1,505 MW | -3 MW | 80 MW | -216 MW |
| 2026-10-08T04:00Z | 576 MW | 1,443 MW | -6 MW | 79 MW | -70 MW |
| 2026-10-08T05:00Z | 575 MW | 1,455 MW | 99 MW | 80 MW | 0 MW |
| 2026-10-08T06:00Z | n/a | n/a | n/a | 78 MW | 156 MW |
| 2026-10-08T07:00Z | 518 MW | 1,490 MW | 408 MW | 78 MW | 255 MW |
| 2026-10-08T08:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-08T09:00Z | 902 MW | 1,460 MW | 306 MW | 78 MW | 0 MW |
| 2026-10-08T10:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-08T11:00Z | 1,960 MW | 559 MW | 164 MW | 77 MW | 0 MW |
| 2026-10-08T12:00Z | 2,380 MW | 487 MW | 166 MW | 78 MW | 0 MW |
| 2026-10-08T13:00Z | 2,843 MW | 526 MW | 173 MW | 81 MW | 0 MW |
| 2026-10-08T14:00Z | 3,204 MW | 460 MW | 301 MW | 82 MW | 10 MW |
| 2026-10-08T15:00Z | 3,560 MW | 517 MW | 367 MW | 55 MW | 35 MW |
| 2026-10-08T16:00Z | 3,702 MW | 552 MW | 413 MW | 41 MW | 57 MW |
| 2026-10-08T17:00Z | 3,836 MW | 440 MW | 423 MW | 41 MW | 83 MW |
| 2026-10-08T18:00Z | 3,886 MW | 495 MW | 435 MW | 41 MW | 103 MW |
| 2026-10-08T19:00Z | 3,925 MW | 511 MW | 445 MW | 41 MW | 44 MW |
| 2026-10-08T20:00Z | 3,764 MW | 394 MW | 423 MW | 41 MW | 6 MW |
| 2026-10-08T21:00Z | 3,614 MW | 263 MW | 256 MW | 41 MW | 7 MW |
| 2026-10-08T22:00Z | 3,565 MW | 314 MW | 244 MW | 41 MW | -193 MW |
| 2026-10-08T23:00Z | 3,341 MW | 406 MW | 237 MW | 41 MW | -227 MW |
| 2026-10-09T00:00Z | 3,303 MW | 408 MW | 238 MW | 41 MW | -225 MW |
| 2026-10-09T01:00Z | 3,196 MW | 452 MW | 240 MW | 41 MW | -223 MW |
| 2026-10-09T02:00Z | 3,201 MW | 491 MW | 240 MW | 41 MW | -183 MW |
| 2026-10-09T03:00Z | 3,153 MW | 474 MW | 205 MW | 41 MW | -143 MW |
| 2026-10-09T04:00Z | 3,301 MW | 461 MW | 256 MW | 41 MW | -142 MW |
| 2026-10-09T05:00Z | 3,356 MW | 429 MW | 257 MW | 41 MW | -141 MW |
| 2026-10-09T06:00Z | 3,424 MW | 365 MW | 185 MW | 41 MW | -70 MW |
| 2026-10-09T07:00Z | 2,828 MW | 385 MW | 163 MW | 41 MW | 74 MW |
| 2026-10-09T08:00Z | 2,546 MW | 396 MW | 164 MW | 41 MW | 49 MW |
| 2026-10-09T09:00Z | 2,528 MW | 352 MW | 170 MW | 41 MW | 53 MW |
| 2026-10-09T10:00Z | 2,872 MW | 351 MW | 175 MW | 41 MW | 75 MW |
| 2026-10-09T11:00Z | 3,104 MW | 343 MW | 221 MW | 41 MW | 92 MW |
| 2026-10-09T12:00Z | 3,201 MW | 341 MW | 235 MW | 48 MW | 45 MW |
| 2026-10-09T13:00Z | 3,355 MW | 349 MW | 298 MW | 70 MW | -144 MW |
| 2026-10-09T14:00Z | 3,305 MW | 339 MW | 316 MW | 65 MW | -143 MW |
| 2026-10-09T15:00Z | 3,388 MW | 350 MW | 300 MW | 60 MW | -71 MW |
| 2026-10-09T16:00Z | 3,540 MW | 363 MW | 305 MW | 44 MW | 15 MW |
| 2026-10-09T17:00Z | 3,431 MW | 293 MW | 164 MW | 41 MW | 176 MW |
| 2026-10-09T18:00Z | 3,178 MW | 263 MW | 167 MW | 41 MW | 188 MW |
| 2026-10-09T19:00Z | 3,062 MW | 324 MW | 167 MW | 41 MW | 116 MW |
| 2026-10-09T20:00Z | 3,289 MW | 331 MW | 169 MW | 41 MW | 7 MW |
| 2026-10-09T21:00Z | 3,251 MW | 300 MW | 172 MW | 41 MW | 0 MW |
| 2026-10-09T22:00Z | 2,970 MW | 264 MW | 170 MW | 41 MW | -37 MW |
| 2026-10-09T23:00Z | 2,999 MW | 280 MW | 166 MW | 41 MW | -74 MW |
| 2026-10-10T00:00Z | 2,800 MW | 320 MW | 164 MW | 41 MW | -146 MW |
| 2026-10-10T01:00Z | 2,649 MW | 380 MW | 57 MW | 41 MW | -145 MW |
| 2026-10-10T02:00Z | 2,718 MW | 387 MW | -5 MW | 41 MW | -144 MW |
| 2026-10-10T03:00Z | 2,652 MW | 395 MW | -5 MW | 41 MW | -142 MW |
| 2026-10-10T04:00Z | 2,430 MW | 457 MW | -5 MW | 74 MW | -142 MW |
| 2026-10-10T05:00Z | 2,233 MW | 537 MW | -5 MW | 81 MW | -105 MW |
| 2026-10-10T06:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-10T07:00Z | 2,142 MW | 401 MW | -3 MW | 55 MW | 30 MW |
| 2026-10-10T08:00Z | 2,039 MW | 387 MW | -3 MW | 41 MW | 55 MW |
| 2026-10-10T09:00Z | 1,702 MW | 429 MW | -3 MW | 62 MW | 35 MW |
| 2026-10-10T10:00Z | 1,438 MW | 451 MW | -3 MW | 70 MW | 16 MW |
| 2026-10-10T11:00Z | 1,449 MW | 468 MW | -3 MW | 71 MW | 20 MW |
| 2026-10-10T12:00Z | 1,537 MW | 483 MW | -3 MW | 74 MW | -108 MW |
| 2026-10-10T13:00Z | 1,504 MW | 490 MW | -3 MW | 81 MW | -141 MW |
| 2026-10-10T14:00Z | 1,617 MW | 426 MW | -3 MW | 79 MW | -35 MW |
| 2026-10-10T15:00Z | 1,740 MW | 510 MW | -3 MW | 82 MW | 0 MW |
| 2026-10-10T16:00Z | 1,639 MW | 812 MW | -3 MW | 81 MW | 117 MW |
| 2026-10-10T17:00Z | n/a | n/a | n/a | 82 MW | 224 MW |
| 2026-10-10T18:00Z | 1,017 MW | 1,350 MW | -3 MW | 77 MW | 251 MW |
| 2026-10-10T19:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-10T20:00Z | 680 MW | 1,325 MW | -3 MW | 78 MW | 149 MW |
| 2026-10-10T21:00Z | 489 MW | 1,457 MW | -3 MW | 79 MW | 5 MW |
| 2026-10-10T22:00Z | 405 MW | 1,466 MW | -3 MW | 80 MW | 0 MW |
| 2026-10-10T23:00Z | 287 MW | 1,462 MW | -3 MW | 79 MW | 0 MW |
| 2026-10-11T00:00Z | 208 MW | 1,472 MW | -3 MW | 81 MW | -112 MW |
| 2026-10-11T01:00Z | 159 MW | 1,469 MW | -3 MW | 79 MW | -149 MW |
| 2026-10-11T02:00Z | 189 MW | 1,479 MW | -3 MW | 80 MW | -148 MW |
| 2026-10-11T03:00Z | 323 MW | 1,380 MW | -3 MW | 78 MW | -148 MW |
| 2026-10-11T04:00Z | 537 MW | 1,233 MW | -3 MW | 80 MW | -146 MW |
| 2026-10-11T05:00Z | 754 MW | 1,138 MW | -3 MW | 80 MW | -146 MW |
| 2026-10-11T06:00Z | 1,025 MW | 802 MW | -3 MW | 80 MW | 0 MW |
| 2026-10-11T07:00Z | 1,249 MW | 809 MW | -3 MW | 80 MW | 0 MW |
| 2026-10-11T08:00Z | 1,525 MW | 894 MW | -3 MW | 81 MW | 0 MW |
| 2026-10-11T09:00Z | 1,893 MW | 875 MW | -5 MW | 80 MW | 0 MW |
| 2026-10-11T10:00Z | 2,400 MW | 664 MW | 74 MW | 77 MW | 0 MW |
| 2026-10-11T11:00Z | 2,748 MW | 485 MW | 139 MW | 42 MW | 0 MW |
| 2026-10-11T12:00Z | 3,029 MW | 483 MW | 179 MW | 43 MW | -72 MW |
| 2026-10-11T13:00Z | 3,274 MW | 564 MW | 176 MW | 63 MW | -143 MW |
| 2026-10-11T14:00Z | 3,263 MW | 607 MW | 202 MW | 78 MW | -143 MW |
| 2026-10-11T15:00Z | 3,185 MW | 720 MW | 362 MW | 80 MW | 3 MW |
| 2026-10-11T16:00Z | 3,212 MW | 739 MW | 431 MW | 79 MW | 13 MW |
| 2026-10-11T17:00Z | n/a | n/a | n/a | 79 MW | 90 MW |
| 2026-10-11T18:00Z | 3,192 MW | 829 MW | 383 MW | 79 MW | 188 MW |
| 2026-10-11T19:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-11T20:00Z | 2,587 MW | 906 MW | 322 MW | 41 MW | 130 MW |
| 2026-10-11T21:00Z | 2,249 MW | 925 MW | 377 MW | 41 MW | 7 MW |
| 2026-10-11T22:00Z | 2,125 MW | 932 MW | 434 MW | 41 MW | -33 MW |
| 2026-10-11T23:00Z | 1,891 MW | 982 MW | 430 MW | 54 MW | -208 MW |
| 2026-10-12T00:00Z | 1,758 MW | 974 MW | 401 MW | 65 MW | -223 MW |
| 2026-10-12T01:00Z | 1,525 MW | 950 MW | 301 MW | 75 MW | -219 MW |
| 2026-10-12T02:00Z | 1,144 MW | 1,174 MW | 356 MW | 76 MW | -216 MW |
| 2026-10-12T03:00Z | 837 MW | 1,322 MW | 319 MW | 77 MW | -215 MW |
| 2026-10-12T04:00Z | 826 MW | 1,381 MW | 308 MW | 78 MW | -70 MW |
| 2026-10-12T05:00Z | 744 MW | 1,405 MW | 271 MW | 77 MW | 0 MW |
| 2026-10-12T06:00Z | 597 MW | 1,403 MW | 281 MW | 78 MW | 10 MW |
| 2026-10-12T07:00Z | 507 MW | 1,384 MW | 406 MW | 79 MW | 10 MW |
| 2026-10-12T08:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-12T09:00Z | 434 MW | 1,487 MW | 356 MW | 80 MW | 102 MW |
| 2026-10-12T10:00Z | 557 MW | 1,451 MW | 302 MW | 77 MW | 92 MW |
| 2026-10-12T11:00Z | 937 MW | 1,298 MW | 193 MW | 77 MW | 3 MW |
| 2026-10-12T12:00Z | 1,490 MW | 673 MW | 164 MW | 78 MW | 0 MW |
| 2026-10-12T13:00Z | 1,686 MW | 463 MW | 171 MW | 41 MW | 0 MW |
| 2026-10-12T14:00Z | 2,461 MW | 651 MW | 179 MW | 66 MW | 0 MW |
| 2026-10-12T15:00Z | 3,275 MW | 694 MW | 220 MW | 80 MW | 0 MW |
| 2026-10-12T16:00Z | 3,659 MW | 719 MW | 398 MW | 80 MW | 86 MW |
| 2026-10-12T17:00Z | 3,740 MW | 706 MW | 435 MW | 80 MW | 212 MW |
| 2026-10-12T18:00Z | 3,590 MW | 930 MW | 436 MW | 81 MW | 214 MW |
| 2026-10-12T19:00Z | 3,465 MW | 800 MW | 379 MW | 77 MW | 144 MW |
| 2026-10-12T20:00Z | 3,723 MW | 677 MW | 202 MW | 79 MW | 44 MW |
| 2026-10-12T21:00Z | 3,630 MW | 446 MW | 194 MW | 65 MW | 0 MW |
| 2026-10-12T22:00Z | 3,464 MW | 365 MW | 164 MW | 41 MW | -112 MW |
| 2026-10-12T23:00Z | 3,260 MW | 368 MW | 165 MW | 41 MW | -224 MW |
| 2026-10-13T00:00Z | 2,960 MW | 386 MW | 168 MW | 41 MW | -221 MW |
| 2026-10-13T01:00Z | 2,903 MW | 390 MW | 52 MW | 41 MW | -219 MW |
| 2026-10-13T02:00Z | 2,901 MW | 396 MW | -5 MW | 41 MW | -216 MW |
| 2026-10-13T03:00Z | 2,795 MW | 385 MW | -5 MW | 41 MW | -215 MW |
| 2026-10-13T04:00Z | 2,618 MW | 393 MW | -3 MW | 41 MW | -142 MW |
| 2026-10-13T05:00Z | 2,569 MW | 376 MW | -3 MW | 41 MW | 0 MW |
| 2026-10-13T06:00Z | 2,948 MW | 399 MW | -3 MW | 41 MW | 117 MW |
| 2026-10-13T07:00Z | 2,882 MW | 407 MW | -4 MW | 41 MW | 227 MW |
| 2026-10-13T08:00Z | 2,892 MW | 409 MW | -8 MW | 41 MW | 227 MW |
| 2026-10-13T09:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-13T10:00Z | 3,219 MW | 412 MW | 237 MW | 41 MW | 29 MW |
| 2026-10-13T11:00Z | 3,143 MW | 393 MW | 367 MW | 41 MW | 0 MW |
| 2026-10-13T12:00Z | 3,004 MW | 410 MW | 324 MW | 41 MW | 0 MW |
| 2026-10-13T13:00Z | 3,016 MW | 413 MW | 279 MW | 41 MW | -112 MW |
| 2026-10-13T14:00Z | 2,867 MW | 422 MW | 204 MW | 41 MW | -149 MW |
| 2026-10-13T15:00Z | 2,490 MW | 424 MW | 187 MW | 41 MW | -148 MW |
| 2026-10-13T16:00Z | 2,142 MW | 529 MW | 294 MW | 50 MW | 80 MW |
| 2026-10-13T17:00Z | 1,589 MW | 806 MW | 413 MW | 75 MW | 215 MW |
| 2026-10-13T18:00Z | 1,435 MW | 971 MW | 436 MW | 80 MW | 179 MW |
| 2026-10-13T19:00Z | 1,565 MW | 882 MW | 418 MW | 79 MW | 178 MW |
| 2026-10-13T20:00Z | 1,618 MW | 750 MW | 348 MW | 77 MW | 130 MW |
| 2026-10-13T21:00Z | 1,670 MW | 504 MW | 242 MW | 78 MW | 0 MW |
| 2026-10-13T22:00Z | 1,840 MW | 323 MW | 171 MW | 52 MW | -38 MW |
| 2026-10-13T23:00Z | 2,124 MW | 330 MW | 176 MW | 41 MW | -149 MW |
| 2026-10-14T00:00Z | 2,488 MW | 331 MW | 178 MW | 41 MW | -148 MW |
| 2026-10-14T01:00Z | 2,628 MW | 309 MW | 168 MW | 41 MW | -148 MW |
| 2026-10-14T02:00Z | 2,993 MW | 314 MW | 176 MW | 41 MW | -146 MW |
| 2026-10-14T03:00Z | 3,200 MW | 315 MW | 200 MW | 41 MW | -145 MW |
| 2026-10-14T04:00Z | 3,303 MW | 329 MW | 297 MW | 41 MW | -145 MW |
| 2026-10-14T05:00Z | 3,561 MW | 395 MW | 326 MW | 41 MW | -108 MW |
| 2026-10-14T06:00Z | 3,790 MW | 438 MW | 305 MW | 41 MW | 27 MW |
| 2026-10-14T07:00Z | 3,918 MW | 479 MW | 326 MW | 41 MW | 40 MW |
| 2026-10-14T08:00Z | 3,953 MW | 423 MW | 363 MW | 41 MW | 5 MW |
| 2026-10-14T09:00Z | 3,861 MW | 361 MW | 338 MW | 41 MW | 6 MW |
| 2026-10-14T10:00Z | 3,844 MW | 486 MW | 354 MW | 41 MW | 8 MW |
| 2026-10-14T11:00Z | 3,912 MW | 484 MW | 353 MW | 41 MW | 2 MW |
| 2026-10-14T12:00Z | 3,935 MW | 484 MW | 354 MW | 41 MW | -144 MW |
| 2026-10-14T13:00Z | 3,813 MW | 447 MW | 266 MW | 41 MW | -143 MW |
| 2026-10-14T14:00Z | 3,847 MW | 459 MW | 304 MW | 41 MW | -142 MW |
| 2026-10-14T15:00Z | 3,931 MW | 458 MW | 384 MW | 41 MW | -106 MW |
| 2026-10-14T16:00Z | 4,136 MW | 489 MW | 404 MW | 41 MW | 35 MW |
| 2026-10-14T17:00Z | 4,129 MW | 468 MW | 349 MW | 41 MW | 203 MW |
| 2026-10-14T18:00Z | 4,029 MW | 503 MW | 213 MW | 41 MW | 250 MW |
| 2026-10-14T19:00Z | 3,753 MW | 536 MW | 235 MW | 41 MW | 288 MW |
| 2026-10-14T20:00Z | 3,377 MW | 373 MW | 164 MW | 41 MW | 106 MW |
| 2026-10-14T21:00Z | 3,242 MW | 291 MW | 164 MW | 41 MW | 0 MW |
| 2026-10-14T22:00Z | 3,005 MW | 318 MW | 187 MW | 41 MW | -74 MW |
| 2026-10-14T23:00Z | 2,508 MW | 382 MW | 94 MW | 41 MW | -189 MW |
| 2026-10-15T00:00Z | 2,524 MW | 448 MW | -5 MW | 41 MW | -294 MW |
| 2026-10-15T01:00Z | 2,404 MW | 433 MW | -5 MW | 41 MW | -291 MW |
| 2026-10-15T02:00Z | 2,168 MW | 449 MW | -5 MW | 41 MW | -286 MW |
| 2026-10-15T03:00Z | 1,847 MW | 557 MW | -5 MW | 41 MW | -281 MW |
| 2026-10-15T04:00Z | 1,217 MW | 775 MW | -6 MW | 41 MW | 0 MW |
| 2026-10-15T05:00Z | 1,121 MW | 1,143 MW | 101 MW | 59 MW | 137 MW |
| 2026-10-15T06:00Z | 1,060 MW | 1,352 MW | 226 MW | 78 MW | 39 MW |
| 2026-10-15T07:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-15T08:00Z | 831 MW | 1,445 MW | 243 MW | 78 MW | 22 MW |
| 2026-10-15T09:00Z | 751 MW | 1,432 MW | 308 MW | 78 MW | 30 MW |
| 2026-10-15T10:00Z | 803 MW | 1,389 MW | 377 MW | 77 MW | 3 MW |
| 2026-10-15T11:00Z | 897 MW | 1,360 MW | 382 MW | 78 MW | 0 MW |
| 2026-10-15T12:00Z | 962 MW | 1,339 MW | 309 MW | 80 MW | -36 MW |
| 2026-10-15T13:00Z | 894 MW | 1,381 MW | 380 MW | 80 MW | -72 MW |
| 2026-10-15T14:00Z | 892 MW | 1,446 MW | 409 MW | 80 MW | -30 MW |
| 2026-10-15T15:00Z | 972 MW | 1,472 MW | 402 MW | 80 MW | 12 MW |
| 2026-10-15T16:00Z | 952 MW | 1,466 MW | 393 MW | 79 MW | 81 MW |
| 2026-10-15T17:00Z | 866 MW | 1,449 MW | 394 MW | 79 MW | 256 MW |
| 2026-10-15T18:00Z | 931 MW | 1,385 MW | 386 MW | 79 MW | 290 MW |
| 2026-10-15T19:00Z | 940 MW | 1,415 MW | 377 MW | 79 MW | 188 MW |
| 2026-10-15T20:00Z | 974 MW | 1,395 MW | 333 MW | 78 MW | 0 MW |
| 2026-10-15T21:00Z | 1,111 MW | 1,331 MW | 178 MW | 79 MW | 0 MW |
| 2026-10-15T22:00Z | 1,198 MW | 1,356 MW | 213 MW | 79 MW | -153 MW |
| 2026-10-15T23:00Z | 1,125 MW | 1,227 MW | 174 MW | 81 MW | -225 MW |
| 2026-10-16T00:00Z | 1,268 MW | 1,312 MW | 169 MW | 80 MW | -223 MW |
| 2026-10-16T01:00Z | 1,300 MW | 1,254 MW | 170 MW | 78 MW | -222 MW |
| 2026-10-16T02:00Z | 1,381 MW | 1,213 MW | 173 MW | 81 MW | -218 MW |
| 2026-10-16T03:00Z | 1,369 MW | 1,171 MW | 172 MW | 81 MW | -216 MW |
| 2026-10-16T04:00Z | 1,464 MW | 1,168 MW | 172 MW | 81 MW | -213 MW |
| 2026-10-16T05:00Z | 1,423 MW | 1,265 MW | 169 MW | 80 MW | 0 MW |
| 2026-10-16T06:00Z | 1,364 MW | 1,325 MW | 176 MW | 78 MW | 109 MW |
| 2026-10-16T07:00Z | 1,320 MW | 1,294 MW | 169 MW | 80 MW | 73 MW |
| 2026-10-16T08:00Z | 1,229 MW | 1,275 MW | 164 MW | 77 MW | 71 MW |
| 2026-10-16T09:00Z | 999 MW | 1,258 MW | 165 MW | 79 MW | 22 MW |
| 2026-10-16T10:00Z | 1,161 MW | 1,002 MW | 80 MW | 77 MW | 0 MW |
| 2026-10-16T11:00Z | 1,402 MW | 591 MW | -5 MW | 61 MW | 0 MW |
| 2026-10-16T12:00Z | 1,567 MW | 645 MW | -5 MW | 41 MW | 0 MW |
| 2026-10-16T13:00Z | 1,851 MW | 640 MW | -5 MW | 41 MW | 0 MW |
| 2026-10-16T14:00Z | 1,749 MW | 802 MW | -8 MW | 41 MW | 0 MW |
| 2026-10-16T15:00Z | 1,590 MW | 1,113 MW | 190 MW | 41 MW | 3 MW |
| 2026-10-16T16:00Z | 1,394 MW | 1,371 MW | 201 MW | 72 MW | 55 MW |
| 2026-10-16T17:00Z | 1,134 MW | 1,369 MW | 300 MW | 78 MW | 192 MW |
| 2026-10-16T18:00Z | 1,243 MW | 1,283 MW | 254 MW | 78 MW | 163 MW |
| 2026-10-16T19:00Z | 1,147 MW | 1,275 MW | 170 MW | 79 MW | 196 MW |
| 2026-10-16T20:00Z | 1,040 MW | 1,317 MW | 169 MW | 80 MW | 116 MW |
| 2026-10-16T21:00Z | 846 MW | 1,323 MW | 247 MW | 79 MW | -74 MW |
| 2026-10-16T22:00Z | 710 MW | 1,339 MW | 260 MW | 80 MW | -148 MW |
| 2026-10-16T23:00Z | 579 MW | 1,351 MW | 206 MW | 81 MW | -147 MW |
| 2026-10-17T00:00Z | 490 MW | 1,357 MW | 223 MW | 80 MW | -146 MW |
| 2026-10-17T01:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-17T02:00Z | 396 MW | 1,347 MW | 246 MW | 79 MW | -145 MW |
| 2026-10-17T03:00Z | 375 MW | 1,324 MW | 176 MW | 79 MW | -144 MW |
| 2026-10-17T04:00Z | 338 MW | 1,328 MW | 172 MW | 81 MW | -142 MW |
| 2026-10-17T05:00Z | 275 MW | 1,353 MW | 168 MW | 80 MW | -36 MW |
| 2026-10-17T06:00Z | 261 MW | 1,418 MW | 307 MW | 80 MW | 7 MW |
| 2026-10-17T07:00Z | 262 MW | 1,490 MW | 371 MW | 81 MW | 87 MW |
| 2026-10-17T08:00Z | 287 MW | 1,446 MW | 360 MW | 79 MW | 103 MW |
| 2026-10-17T09:00Z | 243 MW | 1,375 MW | 267 MW | 78 MW | 0 MW |
| 2026-10-17T10:00Z | 207 MW | 1,141 MW | 164 MW | 78 MW | 0 MW |
| 2026-10-17T11:00Z | 245 MW | 987 MW | 169 MW | 79 MW | -71 MW |
| 2026-10-17T12:00Z | 287 MW | 971 MW | 173 MW | 80 MW | -142 MW |
| 2026-10-17T13:00Z | 268 MW | 976 MW | 170 MW | 79 MW | -142 MW |
| 2026-10-17T14:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-17T15:00Z | 144 MW | 1,282 MW | 168 MW | 79 MW | -32 MW |
| 2026-10-17T16:00Z | 113 MW | 1,456 MW | 390 MW | 80 MW | 179 MW |
| 2026-10-17T17:00Z | 117 MW | 1,496 MW | 425 MW | 78 MW | 259 MW |
| 2026-10-17T18:00Z | 140 MW | 1,526 MW | 462 MW | 80 MW | 274 MW |
| 2026-10-17T19:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-17T20:00Z | 227 MW | 1,500 MW | 427 MW | 80 MW | 121 MW |
| 2026-10-17T21:00Z | 217 MW | 1,457 MW | 375 MW | 78 MW | 0 MW |
| 2026-10-17T22:00Z | 264 MW | 1,360 MW | 310 MW | 78 MW | -38 MW |
| 2026-10-17T23:00Z | 312 MW | 1,344 MW | 334 MW | 79 MW | -112 MW |
| 2026-10-18T00:00Z | 355 MW | 1,339 MW | 270 MW | 80 MW | -148 MW |
| 2026-10-18T01:00Z | 330 MW | 1,345 MW | 281 MW | 80 MW | -146 MW |
| 2026-10-18T02:00Z | 270 MW | 1,331 MW | 293 MW | 79 MW | -146 MW |
| 2026-10-18T03:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-18T04:00Z | 120 MW | 1,355 MW | 265 MW | 80 MW | -144 MW |
| 2026-10-18T05:00Z | 80 MW | 1,368 MW | 311 MW | 80 MW | -143 MW |
| 2026-10-18T06:00Z | 82 MW | 1,449 MW | 394 MW | 80 MW | -142 MW |
| 2026-10-18T07:00Z | 119 MW | 1,492 MW | 380 MW | 79 MW | -36 MW |
| 2026-10-18T08:00Z | 182 MW | 1,494 MW | 370 MW | 80 MW | 0 MW |
| 2026-10-18T09:00Z | 195 MW | 1,447 MW | 290 MW | 78 MW | 0 MW |
| 2026-10-18T10:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-18T11:00Z | 184 MW | 1,141 MW | 176 MW | 82 MW | 0 MW |
| 2026-10-18T12:00Z | 179 MW | 1,139 MW | 173 MW | 81 MW | 0 MW |
| 2026-10-18T13:00Z | 165 MW | 1,079 MW | 174 MW | 81 MW | 0 MW |
| 2026-10-18T14:00Z | 156 MW | 1,129 MW | 169 MW | 80 MW | 0 MW |
| 2026-10-18T15:00Z | 122 MW | 1,350 MW | 266 MW | 80 MW | 0 MW |
| 2026-10-18T16:00Z | 95 MW | 1,524 MW | 358 MW | 79 MW | 105 MW |
| 2026-10-18T17:00Z | 94 MW | 1,500 MW | 401 MW | 77 MW | 271 MW |
| 2026-10-18T18:00Z | 112 MW | 1,538 MW | 424 MW | 80 MW | 293 MW |
| 2026-10-18T19:00Z | 121 MW | 1,534 MW | 432 MW | 80 MW | 290 MW |
| 2026-10-18T20:00Z | 160 MW | 1,545 MW | 427 MW | 80 MW | 105 MW |
| 2026-10-18T21:00Z | 178 MW | 1,487 MW | 380 MW | 78 MW | 0 MW |
| 2026-10-18T22:00Z | 277 MW | 1,426 MW | 363 MW | 78 MW | -152 MW |
| 2026-10-18T23:00Z | 339 MW | 1,414 MW | 326 MW | 79 MW | -226 MW |
| 2026-10-19T00:00Z | 281 MW | 1,387 MW | 340 MW | 81 MW | -224 MW |
| 2026-10-19T01:00Z | 301 MW | 1,422 MW | 365 MW | 81 MW | -221 MW |
| 2026-10-19T02:00Z | 194 MW | 1,439 MW | 381 MW | 80 MW | -220 MW |
| 2026-10-19T03:00Z | 158 MW | 1,420 MW | 343 MW | 79 MW | -218 MW |
| 2026-10-19T04:00Z | 234 MW | 1,451 MW | 352 MW | 80 MW | -215 MW |
| 2026-10-19T05:00Z | 436 MW | 1,471 MW | 359 MW | 80 MW | -70 MW |
| 2026-10-19T06:00Z | 618 MW | 1,510 MW | 398 MW | 81 MW | 7 MW |
| 2026-10-19T07:00Z | 630 MW | 1,434 MW | 426 MW | 77 MW | 120 MW |
| 2026-10-19T08:00Z | 652 MW | 1,391 MW | 434 MW | 65 MW | 182 MW |
| 2026-10-19T09:00Z | 588 MW | 1,442 MW | 425 MW | 60 MW | 221 MW |
| 2026-10-19T10:00Z | 527 MW | 1,459 MW | 398 MW | 77 MW | 3 MW |
| 2026-10-19T11:00Z | 517 MW | 1,512 MW | 376 MW | 80 MW | -73 MW |
| 2026-10-19T12:00Z | 622 MW | 1,470 MW | 313 MW | 79 MW | -74 MW |
| 2026-10-19T13:00Z | 648 MW | 1,447 MW | 289 MW | 80 MW | -71 MW |
| 2026-10-19T14:00Z | 638 MW | 1,434 MW | 247 MW | 79 MW | -71 MW |
| 2026-10-19T15:00Z | 685 MW | 1,451 MW | 302 MW | 79 MW | -71 MW |
| 2026-10-19T16:00Z | 774 MW | 1,483 MW | 358 MW | 78 MW | 55 MW |
| 2026-10-19T17:00Z | 914 MW | 1,474 MW | 360 MW | 79 MW | 133 MW |
| 2026-10-19T18:00Z | 1,118 MW | 1,461 MW | 393 MW | 78 MW | 150 MW |
| 2026-10-19T19:00Z | 1,427 MW | 1,347 MW | 297 MW | 76 MW | 10 MW |
| 2026-10-19T20:00Z | 1,688 MW | 1,184 MW | 170 MW | 81 MW | 0 MW |
| 2026-10-19T21:00Z | 1,793 MW | 1,054 MW | 167 MW | 80 MW | 0 MW |
| 2026-10-19T22:00Z | 1,757 MW | 837 MW | 164 MW | 79 MW | -110 MW |
| 2026-10-19T23:00Z | 1,647 MW | 614 MW | 59 MW | 74 MW | -147 MW |
| 2026-10-20T00:00Z | 1,599 MW | 544 MW | -5 MW | 41 MW | -145 MW |
| 2026-10-20T01:00Z | 1,692 MW | 559 MW | -5 MW | 41 MW | -143 MW |
| 2026-10-20T02:00Z | 1,760 MW | 543 MW | -5 MW | 41 MW | -142 MW |
| 2026-10-20T03:00Z | 1,971 MW | 563 MW | -5 MW | 41 MW | -141 MW |
| 2026-10-20T04:00Z | 2,238 MW | 543 MW | -5 MW | 41 MW | -70 MW |
| 2026-10-20T05:00Z | 2,462 MW | 713 MW | -4 MW | 41 MW | 0 MW |
| 2026-10-20T06:00Z | 2,566 MW | 1,111 MW | -3 MW | 41 MW | 5 MW |
| 2026-10-20T07:00Z | 2,634 MW | 1,101 MW | -3 MW | 41 MW | 49 MW |
| 2026-10-20T08:00Z | 2,586 MW | 1,049 MW | -3 MW | 58 MW | 46 MW |
| 2026-10-20T09:00Z | 2,523 MW | 788 MW | -3 MW | 78 MW | 0 MW |
| 2026-10-20T10:00Z | 2,723 MW | 646 MW | -4 MW | 81 MW | 0 MW |
| 2026-10-20T11:00Z | 2,936 MW | 849 MW | -3 MW | 41 MW | 0 MW |
| 2026-10-20T12:00Z | 2,882 MW | 615 MW | 184 MW | 41 MW | 0 MW |
| 2026-10-20T13:00Z | 2,729 MW | 616 MW | 175 MW | 41 MW | 0 MW |
| 2026-10-20T14:00Z | 2,698 MW | 868 MW | 173 MW | 41 MW | 0 MW |
| 2026-10-20T15:00Z | 2,492 MW | 938 MW | 189 MW | 81 MW | 5 MW |
| 2026-10-20T16:00Z | 2,161 MW | 1,174 MW | 196 MW | 80 MW | 122 MW |
| 2026-10-20T17:00Z | 2,019 MW | 1,126 MW | 172 MW | 81 MW | 267 MW |
| 2026-10-20T18:00Z | 2,037 MW | 1,245 MW | 194 MW | 76 MW | 127 MW |
| 2026-10-20T19:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-20T20:00Z | 2,955 MW | 573 MW | 176 MW | 65 MW | 219 MW |
| 2026-10-20T21:00Z | 2,985 MW | 363 MW | 164 MW | 41 MW | 22 MW |
| 2026-10-20T22:00Z | 2,679 MW | 359 MW | 165 MW | 41 MW | -39 MW |
| 2026-10-20T23:00Z | 2,858 MW | 343 MW | 165 MW | 41 MW | -225 MW |
| 2026-10-21T00:00Z | 2,985 MW | 355 MW | 166 MW | 41 MW | -222 MW |
| 2026-10-21T01:00Z | n/a | n/a | n/a | 41 MW | -218 MW |
| 2026-10-21T02:00Z | 3,052 MW | 405 MW | 191 MW | 41 MW | -216 MW |
| 2026-10-21T03:00Z | 3,063 MW | 355 MW | 175 MW | 41 MW | -216 MW |
| 2026-10-21T04:00Z | 3,299 MW | 434 MW | 170 MW | 41 MW | -176 MW |
| 2026-10-21T05:00Z | 3,418 MW | 380 MW | 169 MW | 41 MW | 0 MW |
| 2026-10-21T06:00Z | 3,411 MW | 779 MW | 267 MW | 41 MW | 13 MW |
| 2026-10-21T07:00Z | 3,580 MW | 1,043 MW | 319 MW | 41 MW | 5 MW |
| 2026-10-21T08:00Z | 3,444 MW | 1,086 MW | 214 MW | 41 MW | 0 MW |
| 2026-10-21T09:00Z | 3,443 MW | 715 MW | 164 MW | 41 MW | 0 MW |
| 2026-10-21T10:00Z | 3,198 MW | 563 MW | 163 MW | 41 MW | 0 MW |
| 2026-10-21T11:00Z | 3,053 MW | 780 MW | 172 MW | 41 MW | 0 MW |
| 2026-10-21T12:00Z | 2,877 MW | 870 MW | 164 MW | 41 MW | 5 MW |
| 2026-10-21T13:00Z | 2,627 MW | 938 MW | 176 MW | 41 MW | 12 MW |
| 2026-10-21T14:00Z | 2,313 MW | 1,149 MW | 372 MW | 41 MW | 13 MW |
| 2026-10-21T15:00Z | 1,829 MW | 1,264 MW | 409 MW | 81 MW | 13 MW |
| 2026-10-21T16:00Z | 1,347 MW | 1,400 MW | 380 MW | 81 MW | 121 MW |
| 2026-10-21T17:00Z | 967 MW | 1,408 MW | 329 MW | 79 MW | 238 MW |
| 2026-10-21T18:00Z | 839 MW | 1,435 MW | 337 MW | 82 MW | 252 MW |
| 2026-10-21T19:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-21T20:00Z | 853 MW | 1,432 MW | 275 MW | 80 MW | 189 MW |
| 2026-10-21T21:00Z | 797 MW | 1,386 MW | 224 MW | 80 MW | -64 MW |
| 2026-10-21T22:00Z | 957 MW | 1,175 MW | 189 MW | 78 MW | -227 MW |
| 2026-10-21T23:00Z | 1,282 MW | 958 MW | 195 MW | 79 MW | -224 MW |
| 2026-10-22T00:00Z | 1,376 MW | 961 MW | 177 MW | 78 MW | -223 MW |
| 2026-10-22T01:00Z | 1,502 MW | 874 MW | 170 MW | 81 MW | -219 MW |
| 2026-10-22T02:00Z | 1,482 MW | 868 MW | 168 MW | 80 MW | -217 MW |
| 2026-10-22T03:00Z | 1,266 MW | 882 MW | 170 MW | 80 MW | -215 MW |
| 2026-10-22T04:00Z | 1,031 MW | 913 MW | 194 MW | 79 MW | -177 MW |
| 2026-10-22T05:00Z | 859 MW | 1,123 MW | 213 MW | 79 MW | 10 MW |
| 2026-10-22T06:00Z | 614 MW | 1,512 MW | 381 MW | 81 MW | 121 MW |
| 2026-10-22T07:00Z | 522 MW | 1,503 MW | 419 MW | 78 MW | 234 MW |
| 2026-10-22T08:00Z | n/a | n/a | n/a | 79 MW | 201 MW |
| 2026-10-22T09:00Z | 323 MW | 1,471 MW | 430 MW | 80 MW | 100 MW |
| 2026-10-22T10:00Z | n/a | n/a | n/a | 78 MW | 0 MW |
| 2026-10-22T11:00Z | n/a | n/a | n/a | 79 MW | -37 MW |
| 2026-10-22T12:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-22T13:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-22T14:00Z | 1,036 MW | 1,219 MW | 347 MW | 79 MW | -73 MW |
| 2026-10-22T15:00Z | 1,315 MW | 1,291 MW | 304 MW | 80 MW | -3 MW |
| 2026-10-22T16:00Z | 1,711 MW | 1,260 MW | 252 MW | 79 MW | 97 MW |
| 2026-10-22T17:00Z | 2,034 MW | 1,306 MW | 251 MW | 82 MW | 138 MW |
| 2026-10-22T18:00Z | 2,131 MW | 1,332 MW | 219 MW | 79 MW | 131 MW |
| 2026-10-22T19:00Z | 2,242 MW | 1,348 MW | 170 MW | 79 MW | 25 MW |
| 2026-10-22T20:00Z | 2,509 MW | 988 MW | 170 MW | 48 MW | 16 MW |
| 2026-10-22T21:00Z | 2,683 MW | 855 MW | 79 MW | 41 MW | 5 MW |
| 2026-10-22T22:00Z | 2,434 MW | 757 MW | -5 MW | 41 MW | -74 MW |
| 2026-10-22T23:00Z | 2,309 MW | 692 MW | -5 MW | 41 MW | -224 MW |
| 2026-10-23T00:00Z | 2,385 MW | 762 MW | -5 MW | 41 MW | -221 MW |
| 2026-10-23T01:00Z | 2,562 MW | 771 MW | -5 MW | 41 MW | -219 MW |
| 2026-10-23T02:00Z | 2,791 MW | 780 MW | -3 MW | 41 MW | -218 MW |
| 2026-10-23T03:00Z | 2,958 MW | 728 MW | -5 MW | 41 MW | -215 MW |
| 2026-10-23T04:00Z | 2,881 MW | 587 MW | 109 MW | 41 MW | -143 MW |
| 2026-10-23T05:00Z | 2,942 MW | 582 MW | 166 MW | 41 MW | 7 MW |
| 2026-10-23T06:00Z | 3,419 MW | 748 MW | 164 MW | 41 MW | 10 MW |
| 2026-10-23T07:00Z | 3,776 MW | 811 MW | 167 MW | 41 MW | 11 MW |
| 2026-10-23T08:00Z | 3,269 MW | 818 MW | 187 MW | 41 MW | 152 MW |
| 2026-10-23T09:00Z | 2,872 MW | 818 MW | 188 MW | 41 MW | 286 MW |
| 2026-10-23T10:00Z | n/a | n/a | n/a | 41 MW | 39 MW |
| 2026-10-23T11:00Z | n/a | n/a | n/a | 41 MW | 16 MW |
| 2026-10-23T12:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-23T13:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-23T14:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-23T15:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-23T16:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-23T17:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-23T18:00Z | 2,447 MW | 832 MW | 164 MW | 48 MW | 100 MW |
| 2026-10-23T19:00Z | 2,263 MW | 815 MW | 170 MW | 63 MW | 258 MW |
| 2026-10-23T20:00Z | 2,019 MW | 1,003 MW | 174 MW | 81 MW | 13 MW |
| 2026-10-23T21:00Z | 1,690 MW | 1,045 MW | 169 MW | 79 MW | 0 MW |
| 2026-10-23T22:00Z | 1,580 MW | 996 MW | 164 MW | 78 MW | 0 MW |
| 2026-10-23T23:00Z | 1,707 MW | 905 MW | 164 MW | 79 MW | -191 MW |
| 2026-10-24T00:00Z | 1,710 MW | 728 MW | 167 MW | 79 MW | -227 MW |
| 2026-10-24T01:00Z | 1,770 MW | 642 MW | 164 MW | 48 MW | -225 MW |
| 2026-10-24T02:00Z | 2,050 MW | 573 MW | 170 MW | 45 MW | -222 MW |
| 2026-10-24T03:00Z | 2,426 MW | 527 MW | 164 MW | 78 MW | -220 MW |
| 2026-10-24T04:00Z | 2,680 MW | 488 MW | -5 MW | 41 MW | -218 MW |
| 2026-10-24T05:00Z | 2,864 MW | 506 MW | -5 MW | 41 MW | -214 MW |
| 2026-10-24T06:00Z | n/a | n/a | n/a | 41 MW | -32 MW |
| 2026-10-24T07:00Z | 3,809 MW | 508 MW | -3 MW | 41 MW | 14 MW |
| 2026-10-24T08:00Z | 3,914 MW | 536 MW | -3 MW | 41 MW | 12 MW |
| 2026-10-24T09:00Z | 3,979 MW | 564 MW | -3 MW | 41 MW | 12 MW |
| 2026-10-24T10:00Z | 4,034 MW | 610 MW | -3 MW | 41 MW | 12 MW |
| 2026-10-24T11:00Z | 4,124 MW | 687 MW | -3 MW | 41 MW | 13 MW |
| 2026-10-24T12:00Z | 3,959 MW | 646 MW | -3 MW | 41 MW | 10 MW |
| 2026-10-24T13:00Z | 3,993 MW | 550 MW | -3 MW | 41 MW | 11 MW |
| 2026-10-24T14:00Z | 3,965 MW | 541 MW | -3 MW | 41 MW | 14 MW |
| 2026-10-24T15:00Z | 3,987 MW | 532 MW | -3 MW | 41 MW | 13 MW |
| 2026-10-24T16:00Z | 3,968 MW | 504 MW | -3 MW | 41 MW | 155 MW |
| 2026-10-24T17:00Z | 3,942 MW | 483 MW | -3 MW | 41 MW | 216 MW |
| 2026-10-24T18:00Z | 3,926 MW | 500 MW | -2 MW | 41 MW | 220 MW |
| 2026-10-24T19:00Z | 3,941 MW | 490 MW | -4 MW | 41 MW | 200 MW |
| 2026-10-24T20:00Z | 3,730 MW | 554 MW | -3 MW | 41 MW | 5 MW |
| 2026-10-24T21:00Z | 3,384 MW | 724 MW | -3 MW | 41 MW | 0 MW |
| 2026-10-24T22:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-24T23:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-25T00:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-25T01:00Z | n/a | n/a | n/a | 41 MW | -189 MW |
| 2026-10-25T02:00Z | 2,708 MW | 819 MW | -3 MW | 41 MW | -222 MW |
| 2026-10-25T03:00Z | 2,439 MW | 805 MW | -3 MW | 41 MW | -220 MW |
| 2026-10-25T04:00Z | 2,523 MW | 832 MW | -3 MW | 41 MW | -217 MW |
| 2026-10-25T05:00Z | 2,590 MW | 829 MW | -3 MW | 41 MW | -215 MW |
| 2026-10-25T06:00Z | 2,515 MW | 831 MW | -3 MW | 41 MW | -35 MW |
| 2026-10-25T07:00Z | 2,421 MW | 827 MW | -3 MW | 41 MW | 0 MW |
| 2026-10-25T08:00Z | 2,339 MW | 851 MW | -3 MW | 41 MW | 0 MW |
| 2026-10-25T09:00Z | n/a | n/a | n/a | 41 MW | 0 MW |
| 2026-10-25T10:00Z | 2,364 MW | 855 MW | -3 MW | 40 MW | 0 MW |
| 2026-10-25T11:00Z | 2,757 MW | 855 MW | -3 MW | 41 MW | 0 MW |
| 2026-10-25T12:00Z | 2,720 MW | 833 MW | -3 MW | 41 MW | 0 MW |
| 2026-10-25T13:00Z | 2,593 MW | 818 MW | -3 MW | 41 MW | 0 MW |
| 2026-10-25T14:00Z | 2,712 MW | 851 MW | -3 MW | 41 MW | 0 MW |
| 2026-10-25T15:00Z | 3,186 MW | 857 MW | -3 MW | 41 MW | 0 MW |
| 2026-10-25T16:00Z | 2,947 MW | 799 MW | -2 MW | 41 MW | 5 MW |
| 2026-10-25T17:00Z | 2,830 MW | 831 MW | -3 MW | 41 MW | 53 MW |
| 2026-10-25T18:00Z | 2,444 MW | 1,041 MW | -3 MW | 78 MW | 167 MW |
| 2026-10-25T19:00Z | 2,050 MW | 1,115 MW | -3 MW | 81 MW | 173 MW |
| 2026-10-25T20:00Z | 1,740 MW | 1,193 MW | -3 MW | 81 MW | 219 MW |
| 2026-10-25T21:00Z | 1,520 MW | 1,120 MW | -3 MW | 81 MW | 220 MW |
| 2026-10-25T22:00Z | 1,477 MW | 895 MW | -3 MW | 77 MW | 203 MW |
| 2026-10-25T23:00Z | 1,655 MW | 620 MW | -3 MW | 73 MW | 166 MW |
| 2026-10-26T00:00Z | 1,870 MW | 861 MW | -3 MW | 74 MW | 7 MW |
| 2026-10-26T01:00Z | 2,321 MW | 631 MW | -3 MW | 78 MW | -40 MW |
| 2026-10-26T02:00Z | 2,652 MW | 774 MW | -3 MW | 80 MW | -229 MW |
| 2026-10-26T03:00Z | 3,039 MW | 641 MW | -3 MW | 80 MW | -227 MW |
| 2026-10-26T04:00Z | 3,062 MW | 575 MW | -3 MW | 54 MW | -224 MW |
| 2026-10-26T05:00Z | 2,963 MW | 616 MW | -3 MW | 41 MW | -221 MW |
| 2026-10-26T06:00Z | 3,267 MW | 649 MW | -3 MW | 41 MW | -218 MW |
| 2026-10-26T07:00Z | 3,526 MW | 617 MW | -3 MW | 41 MW | -108 MW |
| 2026-10-26T08:00Z | n/a | n/a | n/a | 41 MW | -35 MW |
| 2026-10-26T09:00Z | 3,691 MW | n/a | n/a | 41 MW | 5 MW |
| 2026-10-26T10:00Z | 3,693 MW | n/a | n/a | 41 MW | 10 MW |
| 2026-10-26T11:00Z | 3,675 MW | 605 MW | -3 MW | 41 MW | 3 MW |
| 2026-10-26T12:00Z | 3,813 MW | 663 MW | -3 MW | 41 MW | -8 MW |
| 2026-10-26T13:00Z | 3,992 MW | 676 MW | -3 MW | 41 MW | -143 MW |
| 2026-10-26T14:00Z | 3,968 MW | 654 MW | -2 MW | 41 MW | 0 MW |
| 2026-10-26T15:00Z | 3,876 MW | 661 MW | -3 MW | 41 MW | 0 MW |
| 2026-10-26T16:00Z | 4,042 MW | 690 MW | -2 MW | 41 MW | 14 MW |
| 2026-10-26T17:00Z | 4,268 MW | 660 MW | -3 MW | 41 MW | 115 MW |
| 2026-10-26T18:00Z | 4,207 MW | 641 MW | -2 MW | 41 MW | 254 MW |
| 2026-10-26T19:00Z | 4,031 MW | 637 MW | -3 MW | 41 MW | 61 MW |
| 2026-10-26T20:00Z | 3,863 MW | 652 MW | -3 MW | 41 MW | 0 MW |
| 2026-10-26T21:00Z | 3,663 MW | 661 MW | -3 MW | 41 MW | 5 MW |
| 2026-10-26T22:00Z | 3,385 MW | 651 MW | -3 MW | 41 MW | 10 MW |
| 2026-10-26T23:00Z | 3,183 MW | 646 MW | -3 MW | 41 MW | 10 MW |
| 2026-10-27T00:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-27T01:00Z | 3,190 MW | 575 MW | -3 MW | 41 MW | -147 MW |
| 2026-10-27T02:00Z | 3,246 MW | 534 MW | -3 MW | 41 MW | -146 MW |
| 2026-10-27T03:00Z | 3,351 MW | 485 MW | -3 MW | 41 MW | -145 MW |
| 2026-10-27T04:00Z | 3,304 MW | 415 MW | -3 MW | 41 MW | -144 MW |
| 2026-10-27T05:00Z | 3,247 MW | 425 MW | -3 MW | 41 MW | -142 MW |
| 2026-10-27T06:00Z | 3,560 MW | 464 MW | -3 MW | 41 MW | -70 MW |
| 2026-10-27T07:00Z | 3,794 MW | 451 MW | -3 MW | 41 MW | 13 MW |
| 2026-10-27T08:00Z | 3,617 MW | 475 MW | -3 MW | 41 MW | 65 MW |
| 2026-10-27T09:00Z | 3,342 MW | 623 MW | -3 MW | 41 MW | 7 MW |
| 2026-10-27T10:00Z | 3,257 MW | 599 MW | -3 MW | 41 MW | 26 MW |
| 2026-10-27T11:00Z | n/a | n/a | n/a | n/a | n/a |
| 2026-10-27T12:00Z | 3,340 MW | n/a | n/a | 41 MW | 0 MW |
| 2026-10-27T13:00Z | 3,352 MW | 721 MW | -3 MW | 41 MW | 0 MW |
| 2026-10-27T14:00Z | 3,460 MW | 639 MW | -3 MW | 41 MW | 0 MW |
| 2026-10-27T15:00Z | 3,457 MW | 772 MW | -3 MW | 41 MW | 0 MW |
| 2026-10-27T16:00Z | 3,181 MW | 1,040 MW | -3 MW | 41 MW | 38 MW |
| 2026-10-27T17:00Z | 2,972 MW | 1,050 MW | -3 MW | 50 MW | 174 MW |
| 2026-10-27T18:00Z | 3,309 MW | 965 MW | -3 MW | 69 MW | 186 MW |
| 2026-10-27T19:00Z | 3,303 MW | 827 MW | -3 MW | 55 MW | 246 MW |
| 2026-10-27T20:00Z | 3,435 MW | 613 MW | -3 MW | 50 MW | 261 MW |
| 2026-10-27T21:00Z | 3,175 MW | 481 MW | -3 MW | 41 MW | 58 MW |
| 2026-10-27T22:00Z | 3,188 MW | 579 MW | -3 MW | 41 MW | 12 MW |
| 2026-10-27T23:00Z | 3,553 MW | 474 MW | -3 MW | 41 MW | -77 MW |
| 2026-10-28T00:00Z | 3,692 MW | 536 MW | -3 MW | 41 MW | -229 MW |
| 2026-10-28T01:00Z | 3,670 MW | 442 MW | -3 MW | 41 MW | -225 MW |
| 2026-10-28T02:00Z | 3,540 MW | 426 MW | -3 MW | 41 MW | -224 MW |
| 2026-10-28T03:00Z | 3,284 MW | 443 MW | -3 MW | 41 MW | -221 MW |
| 2026-10-28T04:00Z | 3,053 MW | 472 MW | -7 MW | 41 MW | -218 MW |
| 2026-10-28T05:00Z | 2,893 MW | 462 MW | -5 MW | 41 MW | -216 MW |
| 2026-10-28T06:00Z | 2,605 MW | 791 MW | -4 MW | 41 MW | -179 MW |
| 2026-10-28T07:00Z | 2,395 MW | 1,147 MW | -5 MW | 41 MW | 124 MW |
| 2026-10-28T08:00Z | 2,078 MW | 1,286 MW | -5 MW | 80 MW | 143 MW |
| 2026-10-28T09:00Z | n/a | n/a | n/a | 81 MW | 44 MW |
| 2026-10-28T10:00Z | n/a | n/a | n/a | 79 MW | 10 MW |
Source: ENTSO-E Transparency Platform (transparency.entsoe.eu), CC BY 4.0. Aggregated and converted by World Power Monitor; ENTSO-E does not endorse this site. (ENTSO-E Terms of Use plus CC BY 4.0 for listed data items) Data as of 2026-10-28T10:00Z.
Installed Capacity
Annual figure for 2024| Gas | |
|---|---|
| Wind | |
| Oil | |
| Coal | |
| Other |
Total installed capacity in Ireland and Northern Ireland (SEM): 12.7 GW in 2024. Capacity is what could be produced, not what was produced, and each transmission operator reports it once a year.
Source: ENTSO-E Transparency Platform (transparency.entsoe.eu), CC BY 4.0. Aggregated and converted by World Power Monitor; ENTSO-E does not endorse this site. (ENTSO-E Terms of Use plus CC BY 4.0 for listed data items) Data as of 2024.
Day by Day
Daily totals, Europe/Dublin time dates, through 2026-10-26Show the data table (400 rows)
| Date (Europe/Dublin time) | Net generation |
|---|---|
| 2025-09-22 | 51.5 GWh |
| 2025-09-23 | 55.9 GWh |
| 2025-09-24 | 57.9 GWh |
| 2025-09-25 | 65.7 GWh |
| 2025-09-26 | 78.7 GWh |
| 2025-09-27 | 57.0 GWh |
| 2025-09-28 | 45.2 GWh |
| 2025-09-29 | 61.2 GWh |
| 2025-09-30 | 72.6 GWh |
| 2025-10-01 | 77.4 GWh |
| 2025-10-02 | 85.3 GWh |
| 2025-10-03 | 82.7 GWh |
| 2025-10-04 | 80.8 GWh |
| 2025-10-05 | 58.8 GWh |
| 2025-10-06 | 73.8 GWh |
| 2025-10-07 | 67.7 GWh |
| 2025-10-08 | 59.2 GWh |
| 2025-10-09 | 61.5 GWh |
| 2025-10-10 | 52.8 GWh |
| 2025-10-11 | 48.3 GWh |
| 2025-10-12 | n/a |
| 2025-10-13 | 4.68 GWh |
| 2025-10-14 | n/a |
| 2025-10-15 | 4.53 GWh |
| 2025-10-16 | 57.1 GWh |
| 2025-10-17 | 72.9 GWh |
| 2025-10-18 | 80.8 GWh |
| 2025-10-19 | 60.6 GWh |
| 2025-10-20 | 59.4 GWh |
| 2025-10-21 | n/a |
| 2025-10-22 | 54.5 GWh |
| 2025-10-23 | n/a |
| 2025-10-24 | 18.6 GWh |
| 2025-10-25 | 3.00 GWh |
| 2025-10-26 | n/a |
| 2025-10-27 | 23.5 GWh |
| 2025-10-28 | 19.1 GWh |
| 2025-10-29 | n/a |
| 2025-10-30 | n/a |
| 2025-10-31 | 22.9 GWh |
| 2025-11-01 | 56.2 GWh |
| 2025-11-02 | 65.4 GWh |
| 2025-11-03 | n/a |
| 2025-11-04 | n/a |
| 2025-11-05 | 54.8 GWh |
| 2025-11-06 | n/a |
| 2025-11-07 | n/a |
| 2025-11-08 | 3.28 GWh |
| 2025-11-09 | 72.7 GWh |
| 2025-11-10 | n/a |
| 2025-11-11 | n/a |
| 2025-11-12 | n/a |
| 2025-11-13 | n/a |
| 2025-11-14 | n/a |
| 2025-11-15 | 84.0 GWh |
| 2025-11-16 | 68.4 GWh |
| 2025-11-17 | 5.13 GWh |
| 2025-11-18 | 97.1 GWh |
| 2025-11-19 | 95.2 GWh |
| 2025-11-20 | 78.3 GWh |
| 2025-11-21 | 96.9 GWh |
| 2025-11-22 | 75.3 GWh |
| 2025-11-23 | 103 GWh |
| 2025-11-24 | n/a |
| 2025-11-25 | 68.0 GWh |
| 2025-11-26 | 99.2 GWh |
| 2025-11-27 | 111 GWh |
| 2025-11-28 | 104 GWh |
| 2025-11-29 | 78.3 GWh |
| 2025-11-30 | 94.0 GWh |
| 2025-12-01 | 81.4 GWh |
| 2025-12-02 | 94.3 GWh |
| 2025-12-03 | 95.5 GWh |
| 2025-12-04 | 84.4 GWh |
| 2025-12-05 | 107 GWh |
| 2025-12-06 | 89.2 GWh |
| 2025-12-07 | 84.2 GWh |
| 2025-12-08 | 107 GWh |
| 2025-12-09 | 115 GWh |
| 2025-12-10 | 111 GWh |
| 2025-12-11 | 99.0 GWh |
| 2025-12-12 | 3.52 GWh |
| 2025-12-13 | 108 GWh |
| 2025-12-14 | 99.1 GWh |
| 2025-12-15 | 62.3 GWh |
| 2025-12-16 | 76.6 GWh |
| 2025-12-17 | 107 GWh |
| 2025-12-18 | 92.0 GWh |
| 2025-12-19 | 92.5 GWh |
| 2025-12-20 | 102 GWh |
| 2025-12-21 | 60.5 GWh |
| 2025-12-22 | 61.5 GWh |
| 2025-12-23 | 70.5 GWh |
| 2025-12-24 | 86.9 GWh |
| 2025-12-25 | 80.8 GWh |
| 2025-12-26 | 77.9 GWh |
| 2025-12-27 | 83.5 GWh |
| 2025-12-28 | 66.1 GWh |
| 2025-12-29 | 63.7 GWh |
| 2025-12-30 | 77.1 GWh |
| 2025-12-31 | 66.0 GWh |
| 2026-01-01 | 63.8 GWh |
| 2026-01-02 | 76.4 GWh |
| 2026-01-03 | 74.4 GWh |
| 2026-01-04 | 69.5 GWh |
| 2026-01-05 | 77.6 GWh |
| 2026-01-06 | 105 GWh |
| 2026-01-07 | 83.4 GWh |
| 2026-01-08 | 78.4 GWh |
| 2026-01-09 | 77.8 GWh |
| 2026-01-10 | 90.6 GWh |
| 2026-01-11 | 116 GWh |
| 2026-01-12 | 106 GWh |
| 2026-01-13 | 74.3 GWh |
| 2026-01-14 | 109 GWh |
| 2026-01-15 | 84.7 GWh |
| 2026-01-16 | 87.4 GWh |
| 2026-01-17 | 70.1 GWh |
| 2026-01-18 | 92.7 GWh |
| 2026-01-19 | 85.8 GWh |
| 2026-01-20 | 119 GWh |
| 2026-01-21 | 101 GWh |
| 2026-01-22 | 75.1 GWh |
| 2026-01-23 | 108 GWh |
| 2026-01-24 | 95.4 GWh |
| 2026-01-25 | 78.0 GWh |
| 2026-01-26 | n/a |
| 2026-01-27 | 120 GWh |
| 2026-01-28 | 121 GWh |
| 2026-01-29 | n/a |
| 2026-01-30 | 4.95 GWh |
| 2026-01-31 | 72.2 GWh |
| 2026-02-01 | 77.8 GWh |
| 2026-02-02 | n/a |
| 2026-02-03 | n/a |
| 2026-02-04 | 96.3 GWh |
| 2026-02-05 | n/a |
| 2026-02-06 | n/a |
| 2026-02-07 | n/a |
| 2026-02-08 | n/a |
| 2026-02-09 | n/a |
| 2026-02-10 | n/a |
| 2026-02-11 | n/a |
| 2026-02-12 | n/a |
| 2026-02-13 | n/a |
| 2026-02-14 | n/a |
| 2026-02-15 | n/a |
| 2026-02-16 | n/a |
| 2026-02-17 | n/a |
| 2026-02-18 | n/a |
| 2026-02-19 | n/a |
| 2026-02-20 | n/a |
| 2026-02-21 | n/a |
| 2026-02-22 | n/a |
| 2026-02-23 | n/a |
| 2026-02-24 | n/a |
| 2026-02-25 | n/a |
| 2026-02-26 | n/a |
| 2026-02-27 | n/a |
| 2026-02-28 | n/a |
| 2026-03-01 | n/a |
| 2026-03-02 | n/a |
| 2026-03-03 | n/a |
| 2026-03-04 | n/a |
| 2026-03-05 | n/a |
| 2026-03-06 | n/a |
| 2026-03-07 | 89.1 GWh |
| 2026-03-08 | 85.8 GWh |
| 2026-03-09 | n/a |
| 2026-03-10 | 4.19 GWh |
| 2026-03-11 | 4.31 GWh |
| 2026-03-12 | 4.34 GWh |
| 2026-03-13 | 4.51 GWh |
| 2026-03-14 | n/a |
| 2026-03-15 | 3.71 GWh |
| 2026-03-16 | 3.74 GWh |
| 2026-03-17 | n/a |
| 2026-03-18 | n/a |
| 2026-03-19 | n/a |
| 2026-03-20 | n/a |
| 2026-03-21 | n/a |
| 2026-03-22 | n/a |
| 2026-03-23 | n/a |
| 2026-03-24 | n/a |
| 2026-03-25 | n/a |
| 2026-03-26 | n/a |
| 2026-03-27 | n/a |
| 2026-03-28 | 3.01 GWh |
| 2026-03-29 | n/a |
| 2026-03-30 | n/a |
| 2026-03-31 | n/a |
| 2026-04-01 | 4.33 GWh |
| 2026-04-02 | n/a |
| 2026-04-03 | n/a |
| 2026-04-04 | 57.3 GWh |
| 2026-04-05 | n/a |
| 2026-04-06 | 3.75 GWh |
| 2026-04-07 | 4.25 GWh |
| 2026-04-08 | 5.29 GWh |
| 2026-04-09 | n/a |
| 2026-04-10 | 93.7 GWh |
| 2026-04-11 | n/a |
| 2026-04-12 | n/a |
| 2026-04-13 | 5.03 GWh |
| 2026-04-14 | 87.1 GWh |
| 2026-04-15 | 3.89 GWh |
| 2026-04-16 | n/a |
| 2026-04-17 | n/a |
| 2026-04-18 | n/a |
| 2026-04-19 | n/a |
| 2026-04-20 | 55.3 GWh |
| 2026-04-21 | 78.2 GWh |
| 2026-04-22 | 87.8 GWh |
| 2026-04-23 | n/a |
| 2026-04-24 | 64.6 GWh |
| 2026-04-25 | 46.2 GWh |
| 2026-04-26 | n/a |
| 2026-04-27 | 49.0 GWh |
| 2026-04-28 | n/a |
| 2026-04-29 | 67.8 GWh |
| 2026-04-30 | 969 MWh |
| 2026-05-01 | n/a |
| 2026-05-02 | n/a |
| 2026-05-03 | 51.7 GWh |
| 2026-05-04 | 50.6 GWh |
| 2026-05-05 | 51.9 GWh |
| 2026-05-06 | 8.96 GWh |
| 2026-05-07 | 2.63 GWh |
| 2026-05-08 | 50.4 GWh |
| 2026-05-09 | n/a |
| 2026-05-10 | n/a |
| 2026-05-11 | 28.3 GWh |
| 2026-05-12 | 78.0 GWh |
| 2026-05-13 | 91.0 GWh |
| 2026-05-14 | n/a |
| 2026-05-15 | n/a |
| 2026-05-16 | n/a |
| 2026-05-17 | n/a |
| 2026-05-18 | n/a |
| 2026-05-19 | 73.7 GWh |
| 2026-05-20 | n/a |
| 2026-05-21 | 83.3 GWh |
| 2026-05-22 | 72.3 GWh |
| 2026-05-23 | 59.5 GWh |
| 2026-05-24 | 1.76 GWh |
| 2026-05-25 | 43.7 GWh |
| 2026-05-26 | n/a |
| 2026-05-27 | n/a |
| 2026-05-28 | 1.73 GWh |
| 2026-05-29 | 70.4 GWh |
| 2026-05-30 | n/a |
| 2026-05-31 | 60.3 GWh |
| 2026-06-01 | 1.27 GWh |
| 2026-06-02 | n/a |
| 2026-06-03 | n/a |
| 2026-06-04 | 714 MWh |
| 2026-06-05 | 2.47 GWh |
| 2026-06-06 | n/a |
| 2026-06-07 | 1.54 GWh |
| 2026-06-08 | 68.4 GWh |
| 2026-06-09 | 2.17 GWh |
| 2026-06-10 | 2.39 GWh |
| 2026-06-11 | 63.0 GWh |
| 2026-06-12 | n/a |
| 2026-06-13 | 25.4 GWh |
| 2026-06-14 | 2.81 GWh |
| 2026-06-15 | 20.6 GWh |
| 2026-06-16 | 56.9 GWh |
| 2026-06-17 | n/a |
| 2026-06-18 | 70.2 GWh |
| 2026-06-19 | 57.6 GWh |
| 2026-06-20 | 2.86 GWh |
| 2026-06-21 | n/a |
| 2026-06-22 | 48.7 GWh |
| 2026-06-23 | n/a |
| 2026-06-24 | 48.7 GWh |
| 2026-06-25 | 1.76 GWh |
| 2026-06-26 | 1.34 GWh |
| 2026-06-27 | 752 MWh |
| 2026-06-28 | 69.1 GWh |
| 2026-06-29 | 72.3 GWh |
| 2026-06-30 | n/a |
| 2026-07-01 | n/a |
| 2026-07-02 | 59.1 GWh |
| 2026-07-03 | n/a |
| 2026-07-04 | 593 MWh |
| 2026-07-05 | n/a |
| 2026-07-06 | n/a |
| 2026-07-07 | 55.7 GWh |
| 2026-07-08 | n/a |
| 2026-07-09 | n/a |
| 2026-07-10 | 47.4 GWh |
| 2026-07-11 | 435 MWh |
| 2026-07-12 | 50.5 GWh |
| 2026-07-13 | 58.5 GWh |
| 2026-07-14 | 51.9 GWh |
| 2026-07-15 | 45.4 GWh |
| 2026-07-16 | 40.7 GWh |
| 2026-07-17 | 52.7 GWh |
| 2026-07-18 | n/a |
| 2026-07-19 | 37.2 GWh |
| 2026-07-20 | 37 MWh |
| 2026-07-21 | 52.2 GWh |
| 2026-07-22 | n/a |
| 2026-07-23 | 45.9 GWh |
| 2026-07-24 | n/a |
| 2026-07-25 | 60.8 GWh |
| 2026-07-26 | n/a |
| 2026-07-27 | n/a |
| 2026-07-28 | 72.5 GWh |
| 2026-07-29 | 51.2 GWh |
| 2026-07-30 | n/a |
| 2026-07-31 | n/a |
| 2026-08-01 | 944 MWh |
| 2026-08-02 | 42.6 GWh |
| 2026-08-03 | 1.07 GWh |
| 2026-08-04 | 1.38 GWh |
| 2026-08-05 | 916 MWh |
| 2026-08-06 | 2.44 GWh |
| 2026-08-07 | 1.59 GWh |
| 2026-08-08 | 49.2 GWh |
| 2026-08-09 | 44.7 GWh |
| 2026-08-10 | 2.62 GWh |
| 2026-08-11 | 49.8 GWh |
| 2026-08-12 | 639 MWh |
| 2026-08-13 | 661 MWh |
| 2026-08-14 | 52.4 GWh |
| 2026-08-15 | 1.27 GWh |
| 2026-08-16 | 2.37 GWh |
| 2026-08-17 | 63.6 GWh |
| 2026-08-18 | 1.75 GWh |
| 2026-08-19 | 1.65 GWh |
| 2026-08-20 | 1.42 GWh |
| 2026-08-21 | 59.1 GWh |
| 2026-08-22 | 42.8 GWh |
| 2026-08-23 | 38.1 GWh |
| 2026-08-24 | 1.52 GWh |
| 2026-08-25 | 2.21 GWh |
| 2026-08-26 | 56.7 GWh |
| 2026-08-27 | n/a |
| 2026-08-28 | 51.0 GWh |
| 2026-08-29 | 49.7 GWh |
| 2026-08-30 | 48.8 GWh |
| 2026-08-31 | 62.4 GWh |
| 2026-09-01 | n/a |
| 2026-09-02 | n/a |
| 2026-09-03 | 64.3 GWh |
| 2026-09-04 | 74.0 GWh |
| 2026-09-05 | 1.95 GWh |
| 2026-09-06 | 1.12 GWh |
| 2026-09-07 | 968 MWh |
| 2026-09-08 | 407 MWh |
| 2026-09-09 | 734 MWh |
| 2026-09-10 | 1.17 GWh |
| 2026-09-11 | 1.14 GWh |
| 2026-09-12 | 61.9 GWh |
| 2026-09-13 | 41.2 GWh |
| 2026-09-14 | 1.05 GWh |
| 2026-09-15 | 69.0 GWh |
| 2026-09-16 | 72.6 GWh |
| 2026-09-17 | 70.0 GWh |
| 2026-09-18 | 79.8 GWh |
| 2026-09-19 | 63.1 GWh |
| 2026-09-20 | 41.5 GWh |
| 2026-09-21 | 56.8 GWh |
| 2026-09-22 | 56.2 GWh |
| 2026-09-23 | 48.3 GWh |
| 2026-09-24 | 75.9 GWh |
| 2026-09-25 | 65.6 GWh |
| 2026-09-26 | n/a |
| 2026-09-27 | n/a |
| 2026-09-28 | n/a |
| 2026-09-29 | n/a |
| 2026-09-30 | n/a |
| 2026-10-01 | 80.1 GWh |
| 2026-10-02 | 1.27 GWh |
| 2026-10-03 | 2.00 GWh |
| 2026-10-04 | n/a |
| 2026-10-05 | n/a |
| 2026-10-06 | 55.0 GWh |
| 2026-10-07 | n/a |
| 2026-10-08 | n/a |
| 2026-10-09 | 90.9 GWh |
| 2026-10-10 | n/a |
| 2026-10-11 | n/a |
| 2026-10-12 | n/a |
| 2026-10-13 | n/a |
| 2026-10-14 | 102 GWh |
| 2026-10-15 | n/a |
| 2026-10-16 | 64.7 GWh |
| 2026-10-17 | n/a |
| 2026-10-18 | n/a |
| 2026-10-19 | 60.3 GWh |
| 2026-10-20 | n/a |
| 2026-10-21 | n/a |
| 2026-10-22 | n/a |
| 2026-10-23 | n/a |
| 2026-10-24 | n/a |
| 2026-10-25 | n/a |
| 2026-10-26 | 2.42 GWh |
Demand figures for Ireland and Northern Ireland (SEM) stop on 2025-10-22 (22 October 2025), so this chart shows net generation instead.
Source: ENTSO-E Transparency Platform (transparency.entsoe.eu), CC BY 4.0. Aggregated and converted by World Power Monitor; ENTSO-E does not endorse this site. (ENTSO-E Terms of Use plus CC BY 4.0 for listed data items) Data as of 2026-10-26. Daily totals are summed by World Power Monitor from complete Europe/Dublin local days.
Year by Year
Summed from ENTSO-E daily operator data| Year | Demand | Net generation | Largest source | Days reported |
|---|---|---|---|---|
| 2026 (partial) | n/a | 8.03 TWh | Wind 49.9% | 191 |
| 2025 (partial) | 18.7 TWh | 19.1 TWh | Wind 47.4% | 344 |
| 2024 (partial) | 24.3 TWh | 11.4 TWh | Wind 43.3% | 354 |
| 2023 (partial) | 24.7 TWh | 19.2 TWh | Wind 43.6% | 349 |
| 2022 (partial) | 21.8 TWh | 16.2 TWh | Wind 43.6% | 356 |
| 2021 (partial) | 27.6 TWh | 11.0 TWh | Wind 48.3% | 362 |
| 2020 (partial) | 30.2 TWh | 23.3 TWh | Wind 42.3% | 351 |
| 2019 (partial) | 35.1 TWh | 23.1 TWh | Gas 41.2% | 360 |
| 2018 (partial) | 36.1 TWh | 28.1 TWh | Gas 39.8% | 364 |
| 2017 (partial) | 34.0 TWh | 27.1 TWh | Gas 41.4% | 361 |
| 2016 (partial) | 30.1 TWh | 28.9 TWh | Gas 39.7% | 365 |
| 2015 (partial) | 31.2 TWh | 28.2 TWh | Gas 37.2% | 364 |
A year is partial when ENTSO-E has not published every day. Operator totals differ slightly from annual statistics, which are compiled later from plant surveys. Demand and net generation are summed over the days each was reported, so in a year with gaps the two columns can cover different days.
Source: ENTSO-E Transparency Platform (transparency.entsoe.eu), CC BY 4.0. Aggregated and converted by World Power Monitor; ENTSO-E does not endorse this site. (ENTSO-E Terms of Use plus CC BY 4.0 for listed data items) Data as of 2026-10-26.
Power Flows With Neighbours
Net totals, 2026-09-27 (27 September 2026) to 2026-10-26 (26 October 2026)| Neighbour | Direction | Net energy |
|---|---|---|
| Great Britain | Ireland and Northern Ireland (SEM) imports | 66.3 GWh |
Source: ENTSO-E Transparency Platform (transparency.entsoe.eu), CC BY 4.0. Aggregated and converted by World Power Monitor; ENTSO-E does not endorse this site. (ENTSO-E Terms of Use plus CC BY 4.0 for listed data items) Data as of 2026-10-26.
Share and Embed
Figures as of 2026-10-28 (28 October 2026)Download share image (PNG, 1200 x 630 pixels) with the latest demand and largest source for Ireland and Northern Ireland (SEM), credited to ENTSO-E. The image is rebuilt with the page.
Related
Cite this page
World Power Monitor. (2026). Ireland and Northern Ireland (SEM) Electricity Demand and Generation Mix. https://worldpowermonitor.com/zones/ie-sem/
World Power Monitor. Ireland and Northern Ireland (SEM) Electricity Demand and Generation Mix. Data as of 2026-10-28 08:00 UTC. Data from ENTSO-E Transparency Platform. https://worldpowermonitor.com/zones/ie-sem/
@misc{wpm_zones_ie_sem_2026,
title = {{Ireland and Northern Ireland (SEM) Electricity Demand and Generation Mix}},
author = {{World Power Monitor}},
year = {2026},
note = {Data as of 2026-10-28 08:00 UTC. Data from ENTSO-E Transparency Platform.},
url = {https://worldpowermonitor.com/zones/ie-sem/}
} Permalink: https://worldpowermonitor.com/zones/ie-sem/
The Copy buttons add today's date as the access date.